6 years ago

on Wednesday, May 29th 2019, 6:30:00 pm
Work Sanctioned
केन्द्रीय सडक निधि योजना के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र खानपुर में भोवावाली घाट से रायसी की ओर बाण गंगा नदी पर 175 मीटर स्पान प्रीस्ट्रेस्ड आर0सी0सी0 सेतु का निर्माण।

5 years ago

on Tuesday, April 21st 2020, 5:11:22 am

Technical Sanction
of ₹ 903.86 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 881`/235

5 years ago

on Saturday, October 31st 2020, 6:30:00 pm
7.01%
Financial Progress

1st Expenditure
of ₹ 6339337 (63.39 Lacs ) done.
Cummulative ₹ 63.39Lacs ( against 903.86Lacs )

5 years ago

on Monday, November 30th 2020, 6:30:00 pm
15.77%
Financial Progress

2nd Expenditure
of ₹ 7916113 (79.16 Lacs ) done.
Cummulative ₹ 142.55Lacs ( against 903.86Lacs )

5 years ago

on Sunday, January 31st 2021, 6:30:00 pm
20.46%
Financial Progress

3rd Expenditure
of ₹ 4238274 (42.38 Lacs ) done.
Cummulative ₹ 184.94Lacs ( against 903.86Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
45.41%
Financial Progress

4th Expenditure
of ₹ 22551187 (225.51 Lacs ) done.
Cummulative ₹ 410.45Lacs ( against 903.86Lacs )

4 years ago

on Thursday, July 29th 2021, 6:30:00 pm
45.41%
Financial Progress

5th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 410.45Lacs ( against 903.86Lacs )

4 years ago

on Thursday, July 29th 2021, 6:30:00 pm
57.01%
Financial Progress

6th Expenditure
of ₹ 10485288 (104.85 Lacs ) done.
Cummulative ₹ 515.30Lacs ( against 903.86Lacs )

4 years ago

on Monday, August 16th 2021, 7:04:48 am
<span class="4">Picture Id:769</span>
PWD Uttarakahnd
Photo (ID 769) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : 0.175 to 0.350
Remark : Bridge work held up during Rainy season and ponding at working site.

4 years ago

on Monday, August 16th 2021, 7:41:20 am
<span class="4">Picture Id:770</span>
PWD Uttarakahnd
Photo (ID 770) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : 0.150 to 0.350
Remark : सेतु के दोनों ओर जल भराव हो जाने के कारण कार्य वर्तमान में रुका हुआ है।

4 years ago

on Tuesday, August 17th 2021, 6:30:00 pm
70%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Thursday, September 9th 2021, 9:28:46 am
<span class="4">Picture Id:1329</span>
PWD Uttarakahnd
Photo (ID 1329) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : Ch.0.175 to 0.350 Ban Ganga River
Remark : नदी का जल स्तर अधिक होने के कारण सेतु एवं पहुँच मार्ग का कार्य बाधित है।

4 years ago

on Thursday, September 9th 2021, 9:36:10 am
<span class="4">Picture Id:1330</span>
PWD Uttarakahnd
Photo (ID 1330) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : Ban ganga river
Remark : नदी का जलस्तर बढ़ने से कार्य बाधित है।

4 years ago

on Tuesday, September 21st 2021, 8:49:18 am
<span class="4">Picture Id:1481</span>
PWD Uttarakahnd
Photo (ID 1481) from Site Received
Uploader : Amit Kumar Saini, Assistant Engineer Civil ,PD Lansdown
Landmark : Bhovawali ghat
Remark : Work stop due to heavy rainfall

4 years ago

on Tuesday, September 21st 2021, 8:56:53 am
<span class="4">Picture Id:1482</span>
PWD Uttarakahnd
Photo (ID 1482) from Site Received
Uploader : Amit Kumar Saini, Assistant Engineer Civil ,PD Lansdown
Landmark : Banganga river at bhavowali ghat
Remark : Work stoped due to heavy rainfall and river water level up

4 years ago

on Wednesday, October 27th 2021, 6:53:22 am
<span class="4">Picture Id:2857</span>
PWD Uttarakahnd
Photo (ID 2857) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : Ch.0.000 to 0.350
Remark : Slab no 5 casting work in progress

4 years ago

on Wednesday, October 27th 2021, 7:55:03 am
<span class="4">Picture Id:2864</span>
PWD Uttarakahnd
Photo (ID 2864) from Site Received
Uploader : Suresh Babu Pal, Assistant Engineer Civil ,PD Pauri
Landmark : RCC Bridge
Remark : RCC Dack Slab Concrete Work in progress

4 years ago

on Wednesday, October 27th 2021, 9:07:05 am
<span class="4">Picture Id:2867</span>
PWD Uttarakahnd
Photo (ID 2867) from Site Received
Uploader : Suresh Babu Pal, Assistant Engineer Civil ,PD Pauri
Landmark : Bridge
Remark : RCC Slab Concrete work in progress

4 years ago

on Wednesday, October 27th 2021, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Friday, November 12th 2021, 9:13:38 am
<span class="4">Picture Id:3411</span>
PWD Uttarakahnd
Photo (ID 3411) from Site Received
Uploader : Amit Kumar Saini, Assistant Engineer Civil ,PD Lansdown
Landmark : At ब्रिज site
Remark : Bridge inpection by SE

4 years ago

on Friday, November 12th 2021, 9:17:39 am
<span class="4">Picture Id:3412</span>
PWD Uttarakahnd
Photo (ID 3412) from Site Received
Uploader : Amit Kumar Saini, Assistant Engineer Civil ,PD Lansdown
Landmark : At ब्रिज site
Remark : Bridge inpection by SE and EE

4 years ago

on Wednesday, December 29th 2021, 6:30:00 pm
65.91%
Financial Progress

7th Expenditure
of ₹ 8046321 (80.46 Lacs ) done.
Cummulative ₹ 595.77Lacs ( against 903.86Lacs )

4 years ago

on Friday, February 18th 2022, 8:28:18 am
<span class="4">Picture Id:4446</span>
PWD Uttarakahnd
Photo (ID 4446) from Site Received
Uploader : Pardeep Kumar, Additional Assistant Engineer Civil ,CD Laksar
Landmark : Bridge
Remark : Bridge

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
77.41%
Financial Progress

8th Expenditure
of ₹ 10394093 (103.94 Lacs ) done.
Cummulative ₹ 699.71Lacs ( against 903.86Lacs )

3 years ago

on Wednesday, June 29th 2022, 6:30:00 pm
93.35%
Financial Progress

9th Expenditure
of ₹ 14400235 (144.00 Lacs ) done.
Cummulative ₹ 843.71Lacs ( against 903.86Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
99.96%
Financial Progress

10th Expenditure
of ₹ 5977226 (59.77 Lacs ) done.
Cummulative ₹ 903.48Lacs ( against 903.86Lacs )

3 years ago

on Tuesday, January 10th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time