Technical Sanction
of ₹ 2518.09 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4590/277(Hari)

3 years ago

on Tuesday, October 26th 2021, 6:30:00 pm
Work Sanctioned
केन्द्रीय सडक अवसंरचना निधि के अन्तर्गत खानपुर के रूडकी-लक्सर-बालावाली मोटर मार्ग के किमी0 20 से 34 तक चैडीकरण एवं सुदृढीकरण का कार्य।

3 years ago

on Tuesday, March 29th 2022, 6:30:00 pm
5.34%
Financial Progress

1st Expenditure
of ₹ 13450164 (134.50 Lacs ) done.
Cummulative ₹ 134.50Lacs ( against 2518.09Lacs )

3 years ago

on Sunday, May 29th 2022, 6:30:00 pm
11.21%
Financial Progress

2nd Expenditure
of ₹ 14781760 (147.82 Lacs ) done.
Cummulative ₹ 282.32Lacs ( against 2518.09Lacs )

3 years ago

on Monday, August 29th 2022, 6:30:00 pm
40.27%
Financial Progress

3rd Expenditure
of ₹ 73177921 (731.78 Lacs ) done.
Cummulative ₹ 1014.10Lacs ( against 2518.09Lacs )

2 years ago

on Saturday, October 29th 2022, 6:30:00 pm
43.70%
Financial Progress

4th Expenditure
of ₹ 8633646 (86.34 Lacs ) done.
Cummulative ₹ 1100.43Lacs ( against 2518.09Lacs )

2 years ago

on Thursday, December 29th 2022, 6:30:00 pm
50.95%
Financial Progress

5th Expenditure
of ₹ 18264393 (182.64 Lacs ) done.
Cummulative ₹ 1283.08Lacs ( against 2518.09Lacs )

2 years ago

on Monday, January 9th 2023, 2:35:57 am
<span class="4">Picture Id:15308</span>
PWD Uttarakahnd
Photo (ID 15308) from Site Received
Uploader : Sunil Kumar Garg, Superintending Engineer Civil ,Civil Circle Haridwar
Landmark : Core cutting of bm/sdbc in chainage 20.220
Remark : Thickness found 15.180 cm against 16 cm of BM/SDBC

2 years ago

on Wednesday, March 29th 2023, 6:30:00 pm
61.93%
Financial Progress

6th Expenditure
of ₹ 27642392 (276.42 Lacs ) done.
Cummulative ₹ 1559.50Lacs ( against 2518.09Lacs )

2 years ago

on Monday, April 24th 2023, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Tuesday, June 20th 2023, 6:30:00 pm
69.02%
Financial Progress

7th Expenditure
of ₹ 17849822 (178.50 Lacs ) done.
Cummulative ₹ 1738.00Lacs ( against 2518.09Lacs )

2 years ago

on Tuesday, June 27th 2023, 6:30:00 pm
69.02%
Financial Progress

8th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 1738.00Lacs ( against 2518.09Lacs )

2 years ago

on Monday, July 3rd 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, September 11th 2023, 6:30:00 pm
92%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Sunday, September 24th 2023, 6:30:00 pm
76.72%
Financial Progress

10th Expenditure
of ₹ 11590972 (115.91 Lacs ) done.
Cummulative ₹ 1931.83Lacs ( against 2518.09Lacs )

a year ago

on Sunday, September 24th 2023, 6:30:00 pm
72.12%
Financial Progress

9th Expenditure
of ₹ 7792100 (77.92 Lacs ) done.
Cummulative ₹ 1815.92Lacs ( against 2518.09Lacs )

a year ago

on Monday, September 25th 2023, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Friday, September 29th 2023, 6:30:00 pm
76.72%
Financial Progress

11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 1931.83Lacs ( against 2518.09Lacs )

a year ago

on Tuesday, November 21st 2023, 6:30:00 pm
87.19%
Financial Progress

12th Expenditure
of ₹ 26375491 (263.75 Lacs ) done.
Cummulative ₹ 2195.59Lacs ( against 2518.09Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
87.19%
Financial Progress

13th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2195.59Lacs ( against 2518.09Lacs )

a year ago

on Monday, December 18th 2023, 6:30:00 pm
98%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Wednesday, January 10th 2024, 6:30:00 pm
91.80%
Financial Progress

14th Expenditure
of ₹ 11607491 (116.07 Lacs ) done.
Cummulative ₹ 2311.66Lacs ( against 2518.09Lacs )

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Monday, March 25th 2024, 6:30:00 pm
97.76%
Financial Progress

15th Expenditure
of ₹ 15000000 (150.00 Lacs ) done.
Cummulative ₹ 2461.66Lacs ( against 2518.09Lacs )

10 months ago

on Tuesday, May 21st 2024, 6:30:00 pm
97.86%
Financial Progress

16th Expenditure
of ₹ 247623 (2.48 Lacs ) done.
Cummulative ₹ 2464.14Lacs ( against 2518.09Lacs )

10 months ago

on Tuesday, May 21st 2024, 6:30:00 pm
97.95%
Financial Progress

17th Expenditure
of ₹ 223256 (2.23 Lacs ) done.
Cummulative ₹ 2466.37Lacs ( against 2518.09Lacs )

10 months ago

on Tuesday, May 28th 2024, 6:30:00 pm
98.03%
Financial Progress

18th Expenditure
of ₹ 223256 (2.23 Lacs ) done.
Cummulative ₹ 2468.60Lacs ( against 2518.09Lacs )

10 months ago

on Tuesday, May 28th 2024, 6:30:00 pm
98.13%
Financial Progress

19th Expenditure
of ₹ 247623 (2.48 Lacs ) done.
Cummulative ₹ 2471.08Lacs ( against 2518.09Lacs )

9 months ago

on Wednesday, June 5th 2024, 6:30:00 pm
98.23%
Financial Progress

20th Expenditure
of ₹ 247623 (2.48 Lacs ) done.
Cummulative ₹ 2473.56Lacs ( against 2518.09Lacs )

9 months ago

on Sunday, June 30th 2024, 4:57:26 am
<span class="4">Picture Id:49126</span>
PWD Uttarakahnd
Photo (ID 49126) from Site Received
Uploader : Pradeep Kumar, Additional Assistant Engineer Civil ,CD Laksar
Landmark : Laksar Balawali km28. 500
Remark : DBM BC WORK is completed

8 months ago

on Monday, July 1st 2024, 2:45:21 am
<span class="4">Picture Id:49614</span>
PWD Uttarakahnd
Photo (ID 49614) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : 19.800
Remark : BC work completed

8 months ago

on Monday, July 1st 2024, 2:51:12 am
<span class="4">Picture Id:49615</span>
PWD Uttarakahnd
Photo (ID 49615) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : 21.600
Remark : BC work completed

8 months ago

on Monday, July 1st 2024, 3:02:33 am
<span class="4">Picture Id:49620</span>
PWD Uttarakahnd
Photo (ID 49620) from Site Received
Uploader : Lalit Mohan Singh, Assistant Engineer Civil ,CD Laksar
Landmark : 24.200
Remark : SDBC work completed

8 months ago

on Sunday, July 21st 2024, 6:30:00 pm
98.95%
Financial Progress

21st Expenditure
of ₹ 1809868 (18.10 Lacs ) done.
Cummulative ₹ 2491.65Lacs ( against 2518.09Lacs )

7 months ago

on Tuesday, August 6th 2024, 6:30:00 pm
98.95%
Financial Progress

22nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2491.65Lacs ( against 2518.09Lacs )

7 months ago

on Thursday, August 8th 2024, 6:30:00 pm
99.02%
Financial Progress

23rd Expenditure
of ₹ 175820 (1.76 Lacs ) done.
Cummulative ₹ 2493.41Lacs ( against 2518.09Lacs )

6 months ago

on Tuesday, September 24th 2024, 6:30:00 pm
99.02%
Financial Progress

24th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2493.41Lacs ( against 2518.09Lacs )

6 months ago

on Wednesday, September 25th 2024, 6:30:00 pm
99.45%
Financial Progress

25th Expenditure
of ₹ 1084512 (10.85 Lacs ) done.
Cummulative ₹ 2504.26Lacs ( against 2518.09Lacs )

4 months ago

on Thursday, November 21st 2024, 6:30:00 pm
99.71%
Financial Progress

29th Expenditure
of ₹ 223275 (2.23 Lacs ) done.
Cummulative ₹ 2510.86Lacs ( against 2518.09Lacs )

4 months ago

on Thursday, November 21st 2024, 6:30:00 pm
99.45%
Financial Progress

26th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2504.26Lacs ( against 2518.09Lacs )

4 months ago

on Thursday, November 21st 2024, 6:30:00 pm
99.54%
Financial Progress

27th Expenditure
of ₹ 223275 (2.23 Lacs ) done.
Cummulative ₹ 2506.49Lacs ( against 2518.09Lacs )

4 months ago

on Thursday, November 21st 2024, 6:30:00 pm
99.62%
Financial Progress

28th Expenditure
of ₹ 213335 (2.13 Lacs ) done.
Cummulative ₹ 2508.62Lacs ( against 2518.09Lacs )

4 months ago

on Thursday, November 21st 2024, 6:30:00 pm
99.80%
Financial Progress

30th Expenditure
of ₹ 213335 (2.13 Lacs ) done.
Cummulative ₹ 2512.99Lacs ( against 2518.09Lacs )

3 months ago

on Wednesday, December 25th 2024, 6:30:00 pm
99.86%
Financial Progress

31st Expenditure
of ₹ 163430 (1.63 Lacs ) done.
Cummulative ₹ 2514.62Lacs ( against 2518.09Lacs )

2 months ago

on Wednesday, January 1st 2025, 6:30:00 pm
99.86%
Financial Progress

32nd Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 2514.62Lacs ( against 2518.09Lacs )