2 years ago

on Tuesday, July 18th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना वर्ष 2023-24 के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र खानपुर के अन्तर्गत ग्राम मथाना में आन्तरिक गलियों में सी.सी. इन्टरलाॅकिंग टाईल्स का निर्माण कार्य।

2 years ago

on Wednesday, August 2nd 2023, 7:06:58 am

Technical Sanction
of ₹ 57.69 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1846/7C Dt. 02-08-2023

2 years ago

on Monday, December 18th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, January 17th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, January 29th 2024, 6:30:00 pm
28.95%
Financial Progress

1st Expenditure
of ₹ 1670408 (16.70 Lacs ) done.
Cummulative ₹ 16.70Lacs ( against 57.69Lacs )

a year ago

on Tuesday, February 27th 2024, 6:30:00 pm
38.68%
Financial Progress

2nd Expenditure
of ₹ 561101 (5.61 Lacs ) done.
Cummulative ₹ 22.32Lacs ( against 57.69Lacs )

a year ago

on Saturday, March 30th 2024, 6:30:00 pm
40.24%
Financial Progress

3rd Expenditure
of ₹ 90000 (0.90 Lacs ) done.
Cummulative ₹ 23.22Lacs ( against 57.69Lacs )

a year ago

on Sunday, June 30th 2024, 12:52:38 pm
<span class="4">Picture Id:49199</span>
PWD Uttarakahnd
Photo (ID 49199) from Site Received
Uploader : Pardeep Kumar, Additional Assistant Engineer Civil ,CD Laksar
Landmark : Mathana
Remark : CC interlocking tile work is completed

a year ago

on Sunday, June 30th 2024, 1:05:06 pm
<span class="4">Picture Id:49201</span>
PWD Uttarakahnd
Photo (ID 49201) from Site Received
Uploader : Pardeep Kumar, Additional Assistant Engineer Civil ,CD Laksar
Landmark : Mathana
Remark : CC interlocking tile work is completed

a year ago

on Sunday, June 30th 2024, 1:07:12 pm
<span class="4">Picture Id:49203</span>
PWD Uttarakahnd
Photo (ID 49203) from Site Received
Uploader : Pardeep Kumar, Additional Assistant Engineer Civil ,CD Laksar
Landmark : Mathana
Remark : CC interlocking tile work is completed

a year ago

on Saturday, August 10th 2024, 6:30:00 pm
40.24%
Financial Progress

4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 23.22Lacs ( against 57.69Lacs )

a year ago

on Thursday, August 15th 2024, 6:30:00 pm
60.41%
Financial Progress

5th Expenditure
of ₹ 1163507 (11.64 Lacs ) done.
Cummulative ₹ 34.85Lacs ( against 57.69Lacs )

a year ago

on Sunday, September 22nd 2024, 6:30:00 pm
62.02%
Financial Progress

6th Expenditure
of ₹ 92748 (0.93 Lacs ) done.
Cummulative ₹ 35.78Lacs ( against 57.69Lacs )

a year ago

on Tuesday, September 24th 2024, 6:30:00 pm
62.02%
Financial Progress

7th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 35.78Lacs ( against 57.69Lacs )

a year ago

on Wednesday, September 25th 2024, 6:30:00 pm
88.02%
Financial Progress

8th Expenditure
of ₹ 1500000 (15.00 Lacs ) done.
Cummulative ₹ 50.78Lacs ( against 57.69Lacs )

10 months ago

on Wednesday, October 23rd 2024, 6:30:00 pm
92.31%
Financial Progress

9th Expenditure
of ₹ 247614 (2.48 Lacs ) done.
Cummulative ₹ 53.25Lacs ( against 57.69Lacs )

9 months ago

on Monday, November 18th 2024, 6:30:00 pm
96.59%
Financial Progress

10th Expenditure
of ₹ 246814 (2.47 Lacs ) done.
Cummulative ₹ 55.72Lacs ( against 57.69Lacs )