on Thursday, August 22nd 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद हरिद्वार के विधानसभा क्षेत्र लक्सर के ग्राम ऐथल बुजुर्ग में सरदार निशान सिंह के घर से पर्वतीय बस्ती, टिहरी विस्थापित की ओर मार्ग में दो पुलिया व इंटरलोकिंग टाईल्स द्वारा मार्ग का निर्माण कार्य।
on Friday, December 27th 2024, 6:30:00 pm
13.03%
Financial Progress
1st Expenditure
of ₹ 981325 (9.81 Lacs ) done.
Cummulative ₹ 9.81Lacs ( against 75.29Lacs )
on Friday, January 24th 2025, 6:30:00 pm
39.05%
Financial Progress
2nd Expenditure
of ₹ 1959062 (19.59 Lacs ) done.
Cummulative ₹ 29.40Lacs ( against 75.29Lacs )
on Thursday, January 30th 2025, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, February 27th 2025, 6:30:00 pm
45.21%
Financial Progress
3rd Expenditure
of ₹ 463783 (4.64 Lacs ) done.
Cummulative ₹ 34.04Lacs ( against 75.29Lacs )
on Sunday, March 30th 2025, 6:30:00 pm
45.65%
Financial Progress
4th Expenditure
of ₹ 33022 (0.33 Lacs ) done.
Cummulative ₹ 34.37Lacs ( against 75.29Lacs )
on Thursday, May 1st 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, May 28th 2025, 6:30:00 pm
55.35%
Financial Progress
5th Expenditure
of ₹ 729933 (7.30 Lacs ) done.
Cummulative ₹ 41.67Lacs ( against 75.29Lacs )
on Sunday, June 22nd 2025, 6:30:00 pm
86.37%
Financial Progress
6th Expenditure
of ₹ 2335620 (23.36 Lacs ) done.
Cummulative ₹ 65.03Lacs ( against 75.29Lacs )