Refresh data
on Saturday, July 23rd 1927, 8:42:05 am
Technical Sanction
of ₹ 71.2 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 06/EE 2021-22
on Tuesday, September 19th 2006, 6:30:00 pm
Work Sanctioned
पाण्डेगांव-भांकर मोटर मार्ग का नव निर्माण।
on Saturday, February 28th 2009, 6:30:00 pm
0.18%
Financial Progress
1st Expenditure
of ₹ 13000 (0.13 Lacs ) done.
Cummulative ₹ 0.13Lacs ( against 71.2Lacs )
on Tuesday, August 31st 2010, 6:30:00 pm
0.20%
Financial Progress
2nd Expenditure
of ₹ 1430 (0.01 Lacs ) done.
Cummulative ₹ 0.14Lacs ( against 71.2Lacs )
on Friday, November 30th 2018, 6:30:00 pm
1.58%
Financial Progress
3rd Expenditure
of ₹ 98284 (0.98 Lacs ) done.
Cummulative ₹ 1.13Lacs ( against 71.2Lacs )
on Sunday, September 26th 2021, 6:30:00 pm
5.61%
Financial Progress
4th Expenditure
of ₹ 286570 (2.87 Lacs ) done.
Cummulative ₹ 3.99Lacs ( against 71.2Lacs )
on Friday, June 24th 2022, 6:30:00 pm
6.36%
Financial Progress
5th Expenditure
of ₹ 53716 (0.54 Lacs ) done.
Cummulative ₹ 4.53Lacs ( against 71.2Lacs )
on Saturday, July 30th 2022, 10:35:51 am
PWD UttarakahndPhoto (ID 7018) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : Pandygaon bhakar motor road km. 1.00 chain.0.200 Hill site cutting in progress
Remark : Pandygaon bhakar motor km1.00 ch.0.200 Hill site cutting in progress
on Thursday, August 4th 2022, 7:11:18 am
PWD UttarakahndPhoto (ID 7028) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 0.400
Remark : Pandygaon bhakar motor road km 1 ch.0.400 Hill site cutting in progress
on Thursday, August 4th 2022, 7:15:51 am
PWD UttarakahndPhoto (ID 7029) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 0.500
Remark : Pandygaon bhakar motor road km 1 check.500 Hill site cutting
on Thursday, August 4th 2022, 7:24:11 am
PWD UttarakahndPhoto (ID 7031) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 0.700
Remark : Pandygaon bhakar motor road km 1 ch.0.700 Hill site cutting
on Thursday, August 4th 2022, 7:30:04 am
PWD UttarakahndPhoto (ID 7032) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 1.00
Remark : Pandygaon bhakar motor road km 1.00 Hill site cutting
on Thursday, August 4th 2022, 7:34:04 am
PWD UttarakahndPhoto (ID 7033) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 1.100
Remark : Pandygaon bhakar motor road km 1.100
on Thursday, August 4th 2022, 7:43:17 am
PWD UttarakahndPhoto (ID 7034) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 1.375
Remark : Pandygaon bhakar motor road km.1.375 Hill site cutting in progress
on Thursday, August 4th 2022, 7:47:40 am
PWD UttarakahndPhoto (ID 7035) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 1.500
Remark : Pandygaon bhakar motor road km 1.500 Hill site cutting
on Thursday, August 4th 2022, 7:55:37 am
PWD UttarakahndPhoto (ID 7036) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 1.800
Remark : Pandygaon bhakar motor road km 1.800 Hill site cutting in progress
on Thursday, August 4th 2022, 8:47:51 am
PWD UttarakahndPhoto (ID 7038) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 2.00
Remark : Pandygaon bhakar motor road km 2.00 Hill site cutting in progress
on Friday, August 12th 2022, 8:15:16 am
PWD UttarakahndPhoto (ID 7139) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 2.050
Remark : Pandygaon bhakar motor road km 2.050 Hil site cutting in progress
on Friday, August 26th 2022, 5:30:19 am
PWD UttarakahndPhoto (ID 7442) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 2.500
Remark : Pandygaon bhakar motor road km 2.500 Hill site cutting
on Friday, August 26th 2022, 5:36:11 am
PWD UttarakahndPhoto (ID 7443) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 2.650
Remark : Pandygaon bhakar motor road km 2.650 Hill site cutting in progress
on Friday, August 26th 2022, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, September 8th 2022, 6:54:00 am
PWD UttarakahndPhoto (ID 7805) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 2.875
Remark : Pandygaon bhakar motor road km 2.875 Hill site cutting in progress
on Thursday, September 8th 2022, 6:58:07 am
PWD UttarakahndPhoto (ID 7807) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 3.000 km
Remark : Pandygaon bhakar motor road km 3.000 Hill site cutting in progress
on Thursday, September 8th 2022, 7:03:38 am
PWD UttarakahndPhoto (ID 7809) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 3.200
Remark : Pandygaon bhakar motor road km 3.200 Hill site cutting in progress
on Thursday, September 15th 2022, 6:30:00 pm
5.61%
Financial Progress
6th Expenditure
of ₹ -53716 (-0.54 Lacs ) done.
Cummulative ₹ 3.99Lacs ( against 71.2Lacs )
on Tuesday, September 20th 2022, 5:36:57 am
PWD UttarakahndPhoto (ID 8021) from Site Received
Uploader : Lalit Mohan, Additional Assistant Engineer Civil ,TD Bhawali
Landmark : 3.500 km
Remark : Pandygaon bhakar motor road km 3.500 Hill site cutting
on Thursday, September 29th 2022, 6:30:00 pm
19.65%
Financial Progress
7th Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 13.99Lacs ( against 71.2Lacs )
on Sunday, October 30th 2022, 6:30:00 pm
30.92%
Financial Progress
8th Expenditure
of ₹ 801931 (8.02 Lacs ) done.
Cummulative ₹ 22.01Lacs ( against 71.2Lacs )
on Thursday, March 23rd 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, March 30th 2023, 6:30:00 pm
62.45%
Financial Progress
9th Expenditure
of ₹ 2245123 (22.45 Lacs ) done.
Cummulative ₹ 44.46Lacs ( against 71.2Lacs )
on Tuesday, May 30th 2023, 6:30:00 pm
70.31%
Financial Progress
10th Expenditure
of ₹ 560000 (5.60 Lacs ) done.
Cummulative ₹ 50.06Lacs ( against 71.2Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
71.78%
Financial Progress
11th Expenditure
of ₹ 104592 (1.05 Lacs ) done.
Cummulative ₹ 51.11Lacs ( against 71.2Lacs )
on Sunday, December 17th 2023, 6:30:00 pm
72.65%
Financial Progress
12th Expenditure
of ₹ 62000 (0.62 Lacs ) done.
Cummulative ₹ 51.73Lacs ( against 71.2Lacs )
on Saturday, March 30th 2024, 6:30:00 pm
78.25%
Financial Progress
13th Expenditure
of ₹ 398115 (3.98 Lacs ) done.
Cummulative ₹ 55.71Lacs ( against 71.2Lacs )
on Sunday, September 29th 2024, 6:30:00 pm
78.92%
Financial Progress
14th Expenditure
of ₹ 48000 (0.48 Lacs ) done.
Cummulative ₹ 56.19Lacs ( against 71.2Lacs )
on Tuesday, November 26th 2024, 6:30:00 pm
79.33%
Financial Progress
15th Expenditure
of ₹ 29524 (0.30 Lacs ) done.
Cummulative ₹ 56.49Lacs ( against 71.2Lacs )
on Monday, December 30th 2024, 6:30:00 pm
83.06%
Financial Progress
16th Expenditure
of ₹ 264994 (2.65 Lacs ) done.
Cummulative ₹ 59.14Lacs ( against 71.2Lacs )
on Tuesday, March 4th 2025, 6:30:00 pm
83.26%
Financial Progress
18th Expenditure
of ₹ 7812 (0.08 Lacs ) done.
Cummulative ₹ 59.28Lacs ( against 71.2Lacs )
on Tuesday, March 4th 2025, 6:30:00 pm
83.15%
Financial Progress
17th Expenditure
of ₹ 6609 (0.07 Lacs ) done.
Cummulative ₹ 59.20Lacs ( against 71.2Lacs )
on Friday, March 21st 2025, 6:30:00 pm
83.26%
Financial Progress
19th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 59.28Lacs ( against 71.2Lacs )
on Sunday, March 23rd 2025, 6:30:00 pm
85.31%
Financial Progress
20th Expenditure
of ₹ 146371 (1.46 Lacs ) done.
Cummulative ₹ 60.74Lacs ( against 71.2Lacs )