a year ago

on Monday, August 26th 2024, 6:30:00 pm
Work Sanctioned
भीमताल-नौकुचियाताल मोटर मार्ग के किमी0 6 में सडक किनारे दीवार व इण्टर लाॅकिंग टाईल्स का कार्य।

8 months ago

on Friday, January 17th 2025, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 1st time

6 months ago

on Tuesday, March 4th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
33.10%
Financial Progress

1st Expenditure
of ₹ 496500 (4.96 Lacs ) done.
Cummulative ₹ 4.96Lacs ( against 15Lacs )