5 years ago

on Wednesday, March 4th 2020, 6:30:00 pm
Work Sanctioned
वार्षिक योजना 2019-20 के अंतर्गत राष्ट्रीय राजमार्ग संख्या 107(ए ) के किमी 70 से 84.200 के मध्य सुदृढीकरण का कार्य

5 years ago

on Wednesday, March 4th 2020, 6:30:00 pm

Technical Sanction
of ₹ 1198 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. NH-107(A)-UR-2019-20-559

4 years ago

on Tuesday, March 30th 2021, 6:30:00 pm
13.10%
Financial Progress

1st Expenditure
of ₹ 15694602 (156.95 Lacs ) done.
Cummulative ₹ 156.95Lacs ( against 1198.04Lacs )

4 years ago

on Thursday, May 6th 2021, 6:30:00 pm
29.62%
Financial Progress

2nd Expenditure
of ₹ 19795517 (197.96 Lacs ) done.
Cummulative ₹ 354.90Lacs ( against 1198.04Lacs )

4 years ago

on Wednesday, June 23rd 2021, 6:30:00 pm
57.76%
Financial Progress

3rd Expenditure
of ₹ 33707462 (337.07 Lacs ) done.
Cummulative ₹ 691.98Lacs ( against 1198.04Lacs )

4 years ago

on Monday, July 5th 2021, 6:30:00 pm
85.17%

Physical Progress
Physical Progress Reported at 1st time

4 years ago

on Wednesday, July 14th 2021, 8:06:32 am
<span class="4">Picture Id:335</span>
PWD Uttarakahnd
Photo (ID 335) from Site Received
Uploader : Rajbeer Singh Chauhan, Executive Engineer Civil ,PD Gopeshwar
Landmark : Site lab
Remark : Core testing for BC work.

4 years ago

on Friday, July 30th 2021, 6:30:00 pm
86.89%

Physical Progress
Physical Progress Reported at 2nd time

4 years ago

on Sunday, August 15th 2021, 6:30:00 pm
89%

Physical Progress
Physical Progress Reported at 3rd time

4 years ago

on Monday, August 16th 2021, 4:03:08 am
<span class="4">Picture Id:797</span>
PWD Uttarakahnd
Photo (ID 797) from Site Received
Uploader : Prashant Semwal, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 81.350 / near Chunni village
Remark : BC finished layer with KC type drain.

4 years ago

on Monday, August 16th 2021, 4:17:00 am
<span class="4">Picture Id:801</span>
PWD Uttarakahnd
Photo (ID 801) from Site Received
Uploader : Prashant Semwal, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 81.250 / near Chunni village
Remark : Shoulder filling with G.S.B.

4 years ago

on Monday, August 16th 2021, 4:40:48 am
<span class="4">Picture Id:811</span>
PWD Uttarakahnd
Photo (ID 811) from Site Received
Uploader : Prashant Semwal, JE Civil (Samvida) ,NH Div Rudraprayag
Landmark : 82.770/near sansari village
Remark : BC finished layer

4 years ago

on Monday, August 16th 2021, 6:17:45 am
<span class="4">Picture Id:828</span>
PWD Uttarakahnd
Photo (ID 828) from Site Received
Uploader : Shailendra Prasad Tiwari, Additional Assistant Engineer Civil ,NH Div Rudraprayag
Landmark : 80.530/ Chunni bend
Remark : "W" metal beam crash barrier work done

4 years ago

on Monday, August 23rd 2021, 6:30:00 pm
<span class="4">Picture Id: doc279</span>
PWD Uttarakahnd
Photo (ID 279) from Site Received
BC Layer at Km. 81.220

4 years ago

on Tuesday, August 24th 2021, 5:19:43 am
<span class="4">Picture Id:1074</span>
PWD Uttarakahnd
Photo (ID 1074) from Site Received
Uploader : Rajbeer Singh Chauhan, Executive Engineer Civil ,PD Gopeshwar
Landmark : Km 81.220
Remark : Finished BC layer

4 years ago

on Wednesday, August 25th 2021, 6:30:00 pm
70.60%
Financial Progress

4th Expenditure
of ₹ 15386683 (153.87 Lacs ) done.
Cummulative ₹ 845.84Lacs ( against 1198.04Lacs )

3 years ago

on Monday, September 6th 2021, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 4th time

3 years ago

on Friday, September 17th 2021, 9:40:51 pm
<span class="4">Picture Id:1414</span>
PWD Uttarakahnd
Photo (ID 1414) from Site Received
Uploader : Rajbeer Singh Chauhan, Executive Engineer Civil ,PD Gopeshwar
Landmark : Km 83 sansari
Remark : Checking of painted surface by Chief Engineer NH Uttarakhand

3 years ago

on Thursday, December 2nd 2021, 6:30:00 pm
93.51%

Physical Progress
Physical Progress Reported at 5th time

3 years ago

on Wednesday, December 22nd 2021, 1:15:11 am
<span class="4">Picture Id:3839</span>
PWD Uttarakahnd
Photo (ID 3839) from Site Received
Uploader : Rajbeer Singh Chauhan, Executive Engineer Civil ,PD Gopeshwar
Landmark : Km 35.130 kakdagad
Remark : Concreting for substructure

3 years ago

on Wednesday, January 19th 2022, 6:30:00 pm
97.5%

Physical Progress
Physical Progress Reported at 6th time

3 years ago

on Thursday, March 31st 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 7th time

a year ago

on Sunday, September 17th 2023, 8:45:28 am
<span class="4">Picture Id: doc268</span>
PWD Uttarakahnd
Photo (ID 268) from Site Received
DBM work in progress

a year ago

on Sunday, September 17th 2023, 8:45:28 am
<span class="4">Picture Id: doc266</span>
PWD Uttarakahnd
Photo (ID 266) from Site Received
DBM, BC and crash barrier works

a year ago

on Sunday, September 17th 2023, 8:45:28 am
<span class="4">Picture Id: doc265</span>
PWD Uttarakahnd
Photo (ID 265) from Site Received
DBM, BC and crash barrier works

a year ago

on Sunday, September 17th 2023, 8:45:28 am
<span class="4">Picture Id: doc255</span>
PWD Uttarakahnd
Photo (ID 255) from Site Received
DBM and BC Works Completed.