on Monday, February 17th 2020, 6:30:00 pm
Work Sanctioned
उत्तराखण्ड राज्य में ईपीसी मोड के अन्तर्गत राष्ट्रीय राजमार्ग संख्या 125 के किमी0 121.700 से किमी0 129.450 (चम्पावत आबादी भाग), किमी0 136.320 से किमी0 142.00 (लोहाघाट आबादी भाग), किमी0 197.150 से किमी0 202.00 (पिथौरागढ आबादी भाग) में मार्ग सुदृढीकरण का कार्य।
on Tuesday, March 30th 2021, 6:30:00 pm
6.14%
Financial Progress
1st Expenditure
of ₹ 22300000 (223.00 Lacs ) done.
Cummulative ₹ 223.00Lacs ( against 3629.91Lacs )
on Monday, July 12th 2021, 6:30:00 pm
29%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, July 15th 2021, 6:30:00 pm
14.02%
Financial Progress
2nd Expenditure
of ₹ 28600000 (286.00 Lacs ) done.
Cummulative ₹ 509.00Lacs ( against 3629.91Lacs )
on Monday, August 16th 2021, 5:42:52 am
PWD UttarakahndPhoto (ID 721) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : 198.940to 195.50
Remark : Rcc U type construction in pth
on Tuesday, August 17th 2021, 5:48:47 am
PWD UttarakahndPhoto (ID 866) from Site Received
Uploader : Liladhar Mathela, Executive Engineer Civil ,CD Ranikhet
Landmark : Chhatar Champawat
Remark : Inspection
on Wednesday, August 18th 2021, 5:26:37 am
PWD UttarakahndPhoto (ID 1472) from Site Received
Uploader : Hari Nandan Mishra, Assistant Engineer Civil ,CD Ramnagar
Landmark : 141.100
Remark : Near petrol pump
on Monday, September 13th 2021, 4:06:21 am
PWD UttarakahndPhoto (ID 1363) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : Km 202 ch 201.125
Remark : Box drain work in progress
on Friday, September 17th 2021, 6:30:00 pm
35.43%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, September 21st 2021, 8:06:23 am
PWD UttarakahndPhoto (ID 1474) from Site Received
Uploader : Hari Nandan Mishra, Assistant Engineer Civil ,CD Ramnagar
Landmark : 141.200
Remark : G-3
on Tuesday, September 21st 2021, 9:23:33 am
PWD UttarakahndPhoto (ID 1488) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : Ch 201.00
Remark : Utype drain construction
on Tuesday, September 21st 2021, 3:52:17 pm
PWD UttarakahndPhoto (ID 1505) from Site Received
Uploader : Mr Harish Singh Bathiyal, Assistant Engineer Civil ,NH Lohaghat
Landmark : 201
Remark : Sample
on Wednesday, September 29th 2021, 6:30:00 pm
18.19%
Financial Progress
3rd Expenditure
of ₹ 15133000 (151.33 Lacs ) done.
Cummulative ₹ 660.33Lacs ( against 3629.91Lacs )
on Tuesday, October 5th 2021, 6:30:00 pm
37%
Physical Progress
Physical Progress Reported at 3rd time
on Wednesday, October 6th 2021, 3:49:51 am
PWD UttarakahndPhoto (ID 2088) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : Km 201 hec 2-4
Remark : Kc type drain
on Monday, November 29th 2021, 6:30:00 pm
36.38%
Financial Progress
4th Expenditure
of ₹ 66033000 (660.33 Lacs ) done.
Cummulative ₹ 1320.66Lacs ( against 3629.91Lacs )
on Friday, December 3rd 2021, 6:30:00 pm
39.21%
Physical Progress
Physical Progress Reported at 4th time
on Monday, January 3rd 2022, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 5th time
on Saturday, February 19th 2022, 6:56:54 am
PWD UttarakahndPhoto (ID 4389) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : Km 7 hec 8_-10 NH 309A
Remark : Foundation work
on Friday, March 4th 2022, 9:06:35 am
PWD UttarakahndPhoto (ID 4682) from Site Received
Uploader : Dinesh Giriraj, Assistant Engineer Civil ,PD Karnprayag
Landmark : Km 7 hec 8-10
Remark : Counter ford
on Wednesday, May 4th 2022, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 6th time
on Monday, July 25th 2022, 6:30:00 pm
66%
Physical Progress
Physical Progress Reported at 7th time
on Saturday, July 30th 2022, 6:30:00 pm
39.41%
Financial Progress
5th Expenditure
of ₹ 10984000 (109.84 Lacs ) done.
Cummulative ₹ 1430.50Lacs ( against 3629.91Lacs )
on Friday, August 26th 2022, 6:30:00 pm
67%
Physical Progress
Physical Progress Reported at 8th time
on Wednesday, October 26th 2022, 6:30:00 pm
69%
Physical Progress
Physical Progress Reported at 9th time
on Tuesday, January 31st 2023, 6:30:00 pm
44.88%
Financial Progress
6th Expenditure
of ₹ 19850000 (198.50 Lacs ) done.
Cummulative ₹ 1629.00Lacs ( against 3629.91Lacs )
on Thursday, March 23rd 2023, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 10th time
on Wednesday, March 29th 2023, 6:30:00 pm
49.81%
Financial Progress
7th Expenditure
of ₹ 17904000 (179.04 Lacs ) done.
Cummulative ₹ 1808.04Lacs ( against 3629.91Lacs )
on Tuesday, April 18th 2023, 6:30:00 pm
97%
Physical Progress
Physical Progress Reported at 11th time
on Monday, May 8th 2023, 6:30:00 pm
99%
Physical Progress
Physical Progress Reported at 12th time
on Thursday, June 15th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 13th time
on Sunday, July 30th 2023, 6:30:00 pm
58.65%
Financial Progress
8th Expenditure
of ₹ 32100000 (321.00 Lacs ) done.
Cummulative ₹ 2129.04Lacs ( against 3629.91Lacs )