Work Sanctioned
मा0मु0घोषणा संख्या 1351/2015 के अन्तर्गत जनपद पिथौरागढ के विधानसभा क्षेत्र डीडीहाट के अन्तर्गत ग्राम पंचायत सतगढ धर्मशाला तक 4.00 किमी0 मोटर मार्ग नव निर्माण कार्य।
on Friday, January 19th 2018, 6:30:00 pm
Technical Sanction
of ₹ 1.63 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. S.E. ltr No 5242/ 888 C -03 / 2017 dt 20-01-2018
on Wednesday, October 31st 2018, 6:30:00 pm
0.36%
Financial Progress
1st Expenditure
of ₹ 56640 (0.57 Lacs ) done.
Cummulative ₹ 0.57Lacs ( against 155.2Lacs )
on Monday, January 20th 2025, 6:30:00 pm
32.97%
Financial Progress
2nd Expenditure
of ₹ 5060535 (50.61 Lacs ) done.
Cummulative ₹ 51.17Lacs ( against 155.2Lacs )
on Friday, February 21st 2025, 6:30:00 pm
45.15%
Financial Progress
3rd Expenditure
of ₹ 1889694 (18.90 Lacs ) done.
Cummulative ₹ 70.07Lacs ( against 155.2Lacs )
on Sunday, March 16th 2025, 6:30:00 pm
54.11%
Financial Progress
4th Expenditure
of ₹ 1391428 (13.91 Lacs ) done.
Cummulative ₹ 83.98Lacs ( against 155.2Lacs )
on Wednesday, April 9th 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time