on Monday, August 9th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्र्तगत जनपद पिथौरागढ के विधानसभा क्षेत्र पिथौरागढ में नन्ही परी सीमान्त इंजीनियरिंग संस्थान मोटर मार्ग का सुधारीकरण एवं डामरीकरण कार्य।v
on Wednesday, November 10th 2021, 7:34:30 am
Technical Sanction
of ₹ 200.02 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. SE Ltr No 6779/982 C.-03/2021 dt 10/11/2021
on Thursday, June 22nd 2023, 6:30:00 pm
33.20%
Financial Progress
1st Expenditure
of ₹ 6640191 (66.40 Lacs ) done.
Cummulative ₹ 66.40Lacs ( against 200.02Lacs )
on Friday, September 22nd 2023, 6:30:00 pm
55.35%
Financial Progress
2nd Expenditure
of ₹ 4430988 (44.31 Lacs ) done.
Cummulative ₹ 110.71Lacs ( against 200.02Lacs )
on Tuesday, October 24th 2023, 6:30:00 pm
60.95%
Financial Progress
3rd Expenditure
of ₹ 1120000 (11.20 Lacs ) done.
Cummulative ₹ 121.91Lacs ( against 200.02Lacs )
on Friday, November 24th 2023, 6:30:00 pm
64.73%
Financial Progress
4th Expenditure
of ₹ 756597 (7.57 Lacs ) done.
Cummulative ₹ 129.48Lacs ( against 200.02Lacs )
on Thursday, December 14th 2023, 6:30:00 pm
64.85%
Financial Progress
5th Expenditure
of ₹ 23975 (0.24 Lacs ) done.
Cummulative ₹ 129.72Lacs ( against 200.02Lacs )
on Tuesday, December 26th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, November 21st 2024, 6:30:00 pm
66.09%
Financial Progress
6th Expenditure
of ₹ 248508 (2.49 Lacs ) done.
Cummulative ₹ 132.20Lacs ( against 200.02Lacs )
on Thursday, February 6th 2025, 6:30:00 pm
66.19%
Financial Progress
7th Expenditure
of ₹ 19121 (0.19 Lacs ) done.
Cummulative ₹ 132.39Lacs ( against 200.02Lacs )
on Monday, February 10th 2025, 6:30:00 pm
96.19%
Financial Progress
8th Expenditure
of ₹ 6000000 (60.00 Lacs ) done.
Cummulative ₹ 192.39Lacs ( against 200.02Lacs )
on Saturday, March 15th 2025, 6:30:00 pm
96.70%
Financial Progress
9th Expenditure
of ₹ 103151 (1.03 Lacs ) done.
Cummulative ₹ 193.43Lacs ( against 200.02Lacs )