2 years ago

on Monday, December 25th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पिथौरागढ के विधानसभा क्षेत्र डीडीहाट के अन्तर्गत रिण विछुल मोटर मार्ग से पुखरोडा ग्राम के तोक टुपाघर न्यायालय तक मोटर मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-।)

a year ago

on Tuesday, March 19th 2024, 6:30:00 pm
0.41%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 24.27Lacs )

a year ago

on Wednesday, May 22nd 2024, 6:30:00 pm
0.82%
Financial Progress

2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.20Lacs ( against 24.27Lacs )

a year ago

on Friday, July 19th 2024, 6:30:00 pm
33.44%
Financial Progress

3rd Expenditure
of ₹ 791544 (7.92 Lacs ) done.
Cummulative ₹ 8.12Lacs ( against 24.27Lacs )

9 months ago

on Wednesday, November 20th 2024, 6:30:00 pm
52.39%
Financial Progress

4th Expenditure
of ₹ 459900 (4.60 Lacs ) done.
Cummulative ₹ 12.71Lacs ( against 24.27Lacs )

8 months ago

on Thursday, December 12th 2024, 6:30:00 pm
78.38%
Financial Progress

5th Expenditure
of ₹ 630884 (6.31 Lacs ) done.
Cummulative ₹ 19.02Lacs ( against 24.27Lacs )

6 months ago

on Wednesday, March 5th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 1st time

5 months ago

on Tuesday, March 18th 2025, 6:30:00 pm
79.08%
Financial Progress

6th Expenditure
of ₹ 17030 (0.17 Lacs ) done.
Cummulative ₹ 19.19Lacs ( against 24.27Lacs )

4 months ago

on Wednesday, April 9th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

2 months ago

on Tuesday, June 24th 2025, 6:30:00 pm
97.37%
Financial Progress

7th Expenditure
of ₹ 443721 (4.44 Lacs ) done.
Cummulative ₹ 23.63Lacs ( against 24.27Lacs )