Refresh data
on Thursday, July 11th 2019, 6:30:00 pm
Work Sanctioned
कर्णप्रयाग ग्वालदम-जौलजीबी राज्य मार्ग-11 के किमी0 166 (हरडिया नाला) में स्थित क्रोनिक स्लिप जोन का सुरक्षात्मक/उपचार कार्य।
on Thursday, January 14th 2021, 9:03:59 am
Technical Sanction
of ₹ 8.3432 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE letter no-217/04 याता0-अ0/2021
on Monday, October 4th 2021, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, March 8th 2022, 6:30:52 am
PWD UttarakahndPhoto (ID 4764) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.500
Remark : Placing of Gabbion,
Inspection by Ve Almora
on Tuesday, March 8th 2022, 7:04:58 am
PWD UttarakahndPhoto (ID 4765) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.500 of thal- Munsyari road
Remark : Site inspection by C.E sir kumaon region
on Thursday, April 21st 2022, 8:10:00 am
PWD UttarakahndPhoto (ID 5359) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.400
Remark : Hydroseading work in progress at Haradiya
on Thursday, April 21st 2022, 8:27:59 am
PWD UttarakahndPhoto (ID 5538) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.400
Remark : Hydroseading work in progress at Haradiya
on Sunday, May 8th 2022, 11:22:35 am
PWD UttarakahndPhoto (ID 5539) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.5
Remark : 3d netting work in progress at Haradiya (thal-munsyari motar road)
on Thursday, May 19th 2022, 10:30:26 am
PWD UttarakahndPhoto (ID 5601) from Site Received
Uploader : Tara Singh, Assistant Engineer Civil ,PD Didihaat
Landmark : 165.500
Remark : Germination of seeds at Haradiya ( Hydroseading work)
on Monday, May 23rd 2022, 6:30:00 pm
34.51%
Financial Progress
1st Expenditure
of ₹ 28790710 (287.91 Lacs ) done.
Cummulative ₹ 287.91Lacs ( against 834.32Lacs )
on Monday, June 20th 2022, 6:30:00 pm
38.62%
Financial Progress
2nd Expenditure
of ₹ 3430000 (34.30 Lacs ) done.
Cummulative ₹ 322.21Lacs ( against 834.32Lacs )
on Wednesday, June 22nd 2022, 6:30:00 pm
39.27%
Financial Progress
3rd Expenditure
of ₹ 541333 (5.41 Lacs ) done.
Cummulative ₹ 327.62Lacs ( against 834.32Lacs )
on Saturday, January 6th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, August 21st 2024, 6:30:00 pm
39.31%
Financial Progress
4th Expenditure
of ₹ 35437 (0.35 Lacs ) done.
Cummulative ₹ 327.97Lacs ( against 834.32Lacs )
on Wednesday, December 25th 2024, 6:30:00 pm
39.33%
Financial Progress
5th Expenditure
of ₹ 15118 (0.15 Lacs ) done.
Cummulative ₹ 328.13Lacs ( against 834.32Lacs )