2 years ago

on Tuesday, May 2nd 2023, 6:30:00 pm
Work Sanctioned
वित्तीय वर्ष 2023-24 में राज्य योजना के अन्तर्गत जनपद पिथौरागढ़ के विधानसभा क्षेत्र डीडीहाट के अन्तर्गत मसमोली चलमोड़ी मोटर मार्ग का सुधारीकरण व डामरीकरण का कार्य।

2 years ago

on Friday, February 9th 2024, 6:30:00 pm
2%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Tuesday, February 20th 2024, 6:30:00 pm
8.58%
Financial Progress

1st Expenditure
of ₹ 1000000 (10.00 Lacs ) done.
Cummulative ₹ 10.00Lacs ( against 116.55Lacs )

a year ago

on Sunday, March 17th 2024, 6:30:00 pm
31.04%
Financial Progress

3rd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 36.17Lacs ( against 116.55Lacs )

a year ago

on Sunday, March 17th 2024, 6:30:00 pm
30.95%
Financial Progress

2nd Expenditure
of ₹ 2607163 (26.07 Lacs ) done.
Cummulative ₹ 36.07Lacs ( against 116.55Lacs )

a year ago

on Tuesday, April 9th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Tuesday, June 25th 2024, 6:30:00 pm
45%

Physical Progress
Physical Progress Reported at 3rd time

a year ago

on Thursday, June 27th 2024, 7:17:48 am
<span class="4">Picture Id:47665</span>
PWD Uttarakahnd
Photo (ID 47665) from Site Received
Uploader : Gopesh Pandey, JE Civil (Samvida) ,PD Didihaat
Landmark : KM1 Ch-0. 050
Remark : Satisfactory

a year ago

on Friday, July 19th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 4th time

a year ago

on Monday, July 22nd 2024, 6:30:00 pm
32.98%
Financial Progress

4th Expenditure
of ₹ 226472 (2.26 Lacs ) done.
Cummulative ₹ 38.44Lacs ( against 116.55Lacs )

a year ago

on Thursday, July 25th 2024, 6:30:00 pm
34.92%
Financial Progress

5th Expenditure
of ₹ 226472 (2.26 Lacs ) done.
Cummulative ₹ 40.70Lacs ( against 116.55Lacs )

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
34.95%
Financial Progress

6th Expenditure
of ₹ 3597 (0.04 Lacs ) done.
Cummulative ₹ 40.74Lacs ( against 116.55Lacs )

a year ago

on Monday, September 30th 2024, 6:30:00 pm
48.47%
Financial Progress

7th Expenditure
of ₹ 1575692 (15.76 Lacs ) done.
Cummulative ₹ 56.49Lacs ( against 116.55Lacs )

a year ago

on Monday, October 14th 2024, 6:30:00 pm
61.99%
Financial Progress

8th Expenditure
of ₹ 1575692 (15.76 Lacs ) done.
Cummulative ₹ 72.25Lacs ( against 116.55Lacs )

9 months ago

on Thursday, November 21st 2024, 6:30:00 pm
89.35%
Financial Progress

9th Expenditure
of ₹ 3189165 (31.89 Lacs ) done.
Cummulative ₹ 104.14Lacs ( against 116.55Lacs )

9 months ago

on Wednesday, November 27th 2024, 6:30:00 pm
116.72%
Financial Progress

10th Expenditure
of ₹ 3189165 (31.89 Lacs ) done.
Cummulative ₹ 136.03Lacs ( against 116.55Lacs )

9 months ago

on Monday, December 9th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 5th time

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
118.55%
Financial Progress

11th Expenditure
of ₹ 213933 (2.14 Lacs ) done.
Cummulative ₹ 138.17Lacs ( against 116.55Lacs )

7 months ago

on Sunday, February 16th 2025, 6:30:00 pm
118.71%
Financial Progress

12th Expenditure
of ₹ 18505 (0.19 Lacs ) done.
Cummulative ₹ 138.36Lacs ( against 116.55Lacs )

7 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
120.61%
Financial Progress

15th Expenditure
of ₹ 24910 (0.25 Lacs ) done.
Cummulative ₹ 140.57Lacs ( against 116.55Lacs )

7 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
120.40%
Financial Progress

14th Expenditure
of ₹ 89241 (0.89 Lacs ) done.
Cummulative ₹ 140.32Lacs ( against 116.55Lacs )

7 months ago

on Tuesday, February 18th 2025, 6:30:00 pm
119.63%
Financial Progress

13th Expenditure
of ₹ 107352 (1.07 Lacs ) done.
Cummulative ₹ 139.43Lacs ( against 116.55Lacs )

6 months ago

on Friday, February 28th 2025, 6:30:00 pm
129.76%
Financial Progress

16th Expenditure
of ₹ 1066642 (10.67 Lacs ) done.
Cummulative ₹ 151.24Lacs ( against 116.55Lacs )

6 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
130.01%
Financial Progress

18th Expenditure
of ₹ 14160 (0.14 Lacs ) done.
Cummulative ₹ 151.52Lacs ( against 116.55Lacs )

6 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
129.89%
Financial Progress

17th Expenditure
of ₹ 14160 (0.14 Lacs ) done.
Cummulative ₹ 151.38Lacs ( against 116.55Lacs )

6 months ago

on Sunday, March 16th 2025, 6:30:00 pm
130.14%
Financial Progress

19th Expenditure
of ₹ 14927 (0.15 Lacs ) done.
Cummulative ₹ 151.67Lacs ( against 116.55Lacs )

5 months ago

on Wednesday, March 26th 2025, 6:30:00 pm
87.10%
Financial Progress

20th Expenditure
of ₹ -5016000 (-50.16 Lacs ) done.
Cummulative ₹ 101.51Lacs ( against 116.55Lacs )

2 months ago

on Friday, July 4th 2025, 6:30:00 pm
87.35%
Financial Progress

22nd Expenditure
of ₹ 14760 (0.15 Lacs ) done.
Cummulative ₹ 101.81Lacs ( against 116.55Lacs )

2 months ago

on Friday, July 4th 2025, 6:30:00 pm
87.23%
Financial Progress

21st Expenditure
of ₹ 14950 (0.15 Lacs ) done.
Cummulative ₹ 101.66Lacs ( against 116.55Lacs )

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable