a year ago

on Friday, August 16th 2024, 6:30:00 pm
Work Sanctioned
जिला योजना वर्ष 2024-25 के अन्तर्गत मवानी से दारमा मोटर मार्ग के लिए किमी0 1.00 में क्षतिग्रस्त दीवार का मरम्मत कार्य

a year ago

on Friday, September 20th 2024, 6:03:41 am

Technical Sanction
of ₹ 5 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2057/20C

7 months ago

on Monday, February 3rd 2025, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 1st time

6 months ago

on Thursday, February 27th 2025, 6:30:00 pm
2.59%
Financial Progress

1st Expenditure
of ₹ 12936 (0.13 Lacs ) done.
Cummulative ₹ 0.13Lacs ( against 5Lacs )

5 months ago

on Thursday, March 27th 2025, 6:30:00 pm
60.00%
Financial Progress

2nd Expenditure
of ₹ 287064 (2.87 Lacs ) done.
Cummulative ₹ 3.00Lacs ( against 5Lacs )