Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पिथौरागढ़ के विधानसभा क्षेत्र धारचूला क्षेत्र के गामसभा खुमती के घटखोला नाले में खुमती-रौलाताली के मध्य 90 मी0 झूला पुल का निर्माण कार्य (प्रथम चरण) (आर0एफ0क्यू0 एवं टी0ओ0आर0 के अनुसार)
on Sunday, October 20th 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, March 20th 2025, 6:30:00 pm
0.79%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 12.6Lacs )
on Wednesday, April 9th 2025, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, July 18th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, August 5th 2025, 6:30:00 pm
9.49%
Financial Progress
2nd Expenditure
of ₹ 109530 (1.10 Lacs ) done.
Cummulative ₹ 1.20Lacs ( against 12.6Lacs )
on Wednesday, August 6th 2025, 6:30:00 pm
52.95%
Financial Progress
3rd Expenditure
of ₹ 547650 (5.48 Lacs ) done.
Cummulative ₹ 6.67Lacs ( against 12.6Lacs )