on Thursday, January 24th 2019, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद चम्पावत के विधानसभा क्षेत्र लोहाघाट के विकास खण्ड पाटी के अन्तर्गत सलना कानाकोट मोटर मार्ग से सिरमोली लिंक मोटर मार्ग में पुनः निर्माण एवं सुधारीकरण का कार्य।
on Thursday, February 21st 2019, 6:30:00 pm
Technical Sanction
of ₹ 181.28 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 33/SE
on Thursday, February 28th 2019, 6:30:00 pm
0.06%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 181.28Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
41.45%
Financial Progress
2nd Expenditure
of ₹ 7504251 (75.04 Lacs ) done.
Cummulative ₹ 75.14Lacs ( against 181.28Lacs )
on Sunday, July 25th 2021, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, February 27th 2022, 6:30:00 pm
47.52%
Financial Progress
3rd Expenditure
of ₹ 1100000 (11.00 Lacs ) done.
Cummulative ₹ 86.14Lacs ( against 181.28Lacs )
on Monday, April 25th 2022, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, September 29th 2022, 6:30:00 pm
66.53%
Financial Progress
4th Expenditure
of ₹ 3447000 (34.47 Lacs ) done.
Cummulative ₹ 120.61Lacs ( against 181.28Lacs )
on Monday, January 30th 2023, 6:30:00 pm
79.22%
Financial Progress
5th Expenditure
of ₹ 2299842 (23.00 Lacs ) done.
Cummulative ₹ 143.61Lacs ( against 181.28Lacs )
on Wednesday, February 8th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, February 27th 2023, 6:30:00 pm
79.44%
Financial Progress
6th Expenditure
of ₹ 39834 (0.40 Lacs ) done.
Cummulative ₹ 144.01Lacs ( against 181.28Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
90.06%
Financial Progress
7th Expenditure
of ₹ 1925186 (19.25 Lacs ) done.
Cummulative ₹ 163.26Lacs ( against 181.28Lacs )