on Tuesday, November 5th 2024, 6:30:00 pm
Work Sanctioned
सड़क सुरक्षा के अन्तर्गत काठगोदाम खुटानी देवीधूरा पंचेश्वर मोटर मार्ग (राज्य मार्ग संख्या-10) के कि.मी. 93 (वालिक) से कि.मी. 117 (पाटी) तक सड़क सुरक्षा के कार्य।
on Sunday, March 9th 2025, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, March 22nd 2025, 6:30:00 pm
96.03%
Financial Progress
1st Expenditure
of ₹ 47410748 (474.11 Lacs ) done.
Cummulative ₹ 474.11Lacs ( against 493.7Lacs )
on Tuesday, May 27th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Friday, June 27th 2025, 6:30:00 pm
98.00%
Financial Progress
2nd Expenditure
of ₹ 972202 (9.72 Lacs ) done.
Cummulative ₹ 483.83Lacs ( against 493.7Lacs )