Work Sanctioned
मा0 मुख्यमंत्री घोषण सं0 479/2023 के अन्तर्गत मरोड़ाखान से एबटमैन्ट मोटर मार्ग में पुनः निर्माण एवं सुधारीकरण का कार्य
on Tuesday, January 21st 2025, 6:30:00 pm
1%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, February 2nd 2025, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, February 18th 2025, 6:30:00 pm
14.35%
Financial Progress
1st Expenditure
of ₹ 2010536 (20.11 Lacs ) done.
Cummulative ₹ 20.11Lacs ( against 140.07Lacs )
on Tuesday, March 4th 2025, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, March 20th 2025, 6:30:00 pm
14.43%
Financial Progress
2nd Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 20.21Lacs ( against 140.07Lacs )
on Wednesday, May 28th 2025, 6:30:00 pm
16.16%
Financial Progress
3rd Expenditure
of ₹ 243126 (2.43 Lacs ) done.
Cummulative ₹ 22.64Lacs ( against 140.07Lacs )
on Thursday, June 26th 2025, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 4th time
on Friday, June 27th 2025, 6:30:00 pm
16.16%
Financial Progress
4th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 22.64Lacs ( against 140.07Lacs )
on Monday, June 30th 2025, 6:30:00 pm
33.63%
Financial Progress
5th Expenditure
of ₹ 2446900 (24.47 Lacs ) done.
Cummulative ₹ 47.11Lacs ( against 140.07Lacs )
on Monday, July 14th 2025, 12:30:48 pm
PWD UttarakahndPhoto (ID 80015) from Site Received
Uploader : Hitesh Kandpal, Executive Engineer Civil ,CD Lohaghat
Landmark : 2.300
Remark : Tile work
on Monday, July 14th 2025, 12:32:00 pm
PWD UttarakahndPhoto (ID 80016) from Site Received
Uploader : Hitesh Kandpal, Executive Engineer Civil ,CD Lohaghat
Landmark : 2.4
Remark : Inter locking tiles