on Sunday, January 3rd 2021, 6:30:00 pm
Work Sanctioned
ग्राम पंचायत खर्ककार्की में नौलाटाक से सक्टी तोक तक मार्ग का पुनः निर्माण एवं सुधारीकरण कार्य।
on Thursday, January 28th 2021, 6:30:00 pm
Technical Sanction
of ₹ 20 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 200/T.S.
on Tuesday, January 30th 2024, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 20Lacs )
on Saturday, February 3rd 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, February 28th 2024, 6:30:00 pm
49.77%
Financial Progress
2nd Expenditure
of ₹ 995348 (9.95 Lacs ) done.
Cummulative ₹ 9.95Lacs ( against 20Lacs )