2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
Work Sanctioned
जिला योजना वर्ष 2023-24 के अन्तर्गत वार्ड न0-7 नागनाथ में नसरी गेट से सर्किट हाउस तक सम्पर्क मार्ग में नाली निर्माण व मरम्मत कार्य।

2 years ago

on Tuesday, January 30th 2024, 6:30:00 pm
40.00%
Financial Progress

1st Expenditure
of ₹ 600000 (6.00 Lacs ) done.
Cummulative ₹ 6.00Lacs ( against 15Lacs )

2 years ago

on Saturday, February 3rd 2024, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Friday, August 23rd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

10 months ago

on Wednesday, October 30th 2024, 6:30:00 pm
92.09%
Financial Progress

2nd Expenditure
of ₹ 781294 (7.81 Lacs ) done.
Cummulative ₹ 13.81Lacs ( against 15Lacs )