on Monday, September 25th 2023, 6:30:00 pm
Work Sanctioned
सर्किट हाउस के विस्ताीकरण/उच्चीकरण/अनुरक्षण सम्बन्धी कार्य।
on Wednesday, May 29th 2024, 6:30:00 pm
0.30%
Financial Progress
1st Expenditure
of ₹ 248000 (2.48 Lacs ) done.
Cummulative ₹ 2.48Lacs ( against 820.096Lacs )
on Monday, December 30th 2024, 6:30:00 pm
5.33%
Financial Progress
2nd Expenditure
of ₹ 4124449 (41.24 Lacs ) done.
Cummulative ₹ 43.72Lacs ( against 820.096Lacs )
on Thursday, January 30th 2025, 6:30:00 pm
8.77%
Financial Progress
3rd Expenditure
of ₹ 2817485 (28.17 Lacs ) done.
Cummulative ₹ 71.90Lacs ( against 820.096Lacs )
on Sunday, March 9th 2025, 8:46:44 am
PWD UttarakahndPhoto (ID 65611) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Circuit house second floor
Remark : Beam casting in progress
on Tuesday, March 18th 2025, 8:28:42 am
PWD UttarakahndPhoto (ID 66004) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Second floor
Remark : Second floor column casting in progress
on Tuesday, March 18th 2025, 8:30:12 am
PWD UttarakahndPhoto (ID 66005) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Retro fitting
Remark : Retro fitting work in progress
on Wednesday, March 26th 2025, 5:27:33 am
PWD UttarakahndPhoto (ID 66538) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing of columns
Remark : Retro fitting work in progress
on Wednesday, March 26th 2025, 5:29:43 am
PWD UttarakahndPhoto (ID 66539) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing
Remark : Retro fitting work in progress
on Thursday, March 27th 2025, 7:38:04 am
PWD UttarakahndPhoto (ID 66601) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Circuit House 2 nd floor
Remark : Beam reinforcement
on Thursday, March 27th 2025, 7:39:10 am
PWD UttarakahndPhoto (ID 66602) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Circuit House reinforcement
Remark : Beam reinforcement
on Sunday, March 30th 2025, 6:30:00 pm
12.13%
Financial Progress
4th Expenditure
of ₹ 2757252 (27.57 Lacs ) done.
Cummulative ₹ 99.47Lacs ( against 820.096Lacs )
on Thursday, April 3rd 2025, 6:22:55 am
PWD UttarakahndPhoto (ID 66829) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Foundation
Remark : Retro fitting work in foundation under progress
on Thursday, April 3rd 2025, 6:34:56 am
PWD UttarakahndPhoto (ID 66834) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Foundation
Remark : Retro fitting work F13 grid 9-9 in progress
on Saturday, April 5th 2025, 9:52:04 am
PWD UttarakahndPhoto (ID 67002) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing
Remark : Retro fitting work in progress footing along grid 9-9
on Tuesday, April 8th 2025, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Monday, April 14th 2025, 8:58:59 am
PWD UttarakahndPhoto (ID 67316) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing
Remark : Footing casting in progress
on Monday, April 14th 2025, 9:03:11 am
PWD UttarakahndPhoto (ID 67317) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing
Remark : Footing retro fitting in progress
on Tuesday, April 22nd 2025, 5:36:23 am
PWD UttarakahndPhoto (ID 67836) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Footing
Remark : Retro fitting work in progress
on Friday, May 2nd 2025, 5:34:16 am
PWD UttarakahndPhoto (ID 69190) from Site Received
Uploader : Deep Chandra, Assistant Engineer Civil ,PD Champawat
Landmark : Foundation
Remark : Foundation work in progress
on Sunday, June 29th 2025, 6:30:00 pm
20.67%
Financial Progress
5th Expenditure
of ₹ 7005997 (70.06 Lacs ) done.
Cummulative ₹ 169.53Lacs ( against 820.096Lacs )
on Thursday, July 3rd 2025, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, July 30th 2025, 6:30:00 pm
27.50%
Financial Progress
6th Expenditure
of ₹ 5600000 (56.00 Lacs ) done.
Cummulative ₹ 225.53Lacs ( against 820.096Lacs )