Work Sanctioned
जिला योजना वर्ष 2024-25 के अन्तर्गत फंुगर में मंच-तामली सड़क से ज्याड़ा तोक तक कच्ची सड़क में पक्की नाली व स्कपर निर्माण कार्य।

8 months ago

on Monday, December 30th 2024, 6:30:00 pm
3.90%
Financial Progress

1st Expenditure
of ₹ 23426 (0.23 Lacs ) done.
Cummulative ₹ 0.23Lacs ( against 6Lacs )

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
62.05%
Financial Progress

2nd Expenditure
of ₹ 348881 (3.49 Lacs ) done.
Cummulative ₹ 3.72Lacs ( against 6Lacs )

5 months ago

on Monday, April 7th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time