10 months ago

on Thursday, October 17th 2024, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा-554/2023 के अन्तर्गत जनपद चम्पावत के विधानसभा क्षेत्र लोहाघाट में टाक खंदक करौली मोटर मार्ग का सुधारीकरण/ डामरीकरण का कार्य।

6 months ago

on Tuesday, March 4th 2025, 6:57:55 am
<span class="4">Picture Id:65325</span>
PWD Uttarakahnd
Photo (ID 65325) from Site Received
Uploader : Pankaj Rai, Assistant Engineer Civil ,PD Champawat
Landmark : Km 2.100
Remark : Extra cutting work in progress

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
11.16%
Financial Progress

1st Expenditure
of ₹ 4719444 (47.19 Lacs ) done.
Cummulative ₹ 47.19Lacs ( against 423.02Lacs )

4 months ago

on Thursday, May 1st 2025, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 1st time

3 months ago

on Friday, May 30th 2025, 6:30:00 pm
12.00%
Financial Progress

2nd Expenditure
of ₹ 354932 (3.55 Lacs ) done.
Cummulative ₹ 50.74Lacs ( against 423.02Lacs )

2 months ago

on Sunday, June 29th 2025, 6:30:00 pm
12.48%
Financial Progress

3rd Expenditure
of ₹ 206260 (2.06 Lacs ) done.
Cummulative ₹ 52.81Lacs ( against 423.02Lacs )

2 months ago

on Monday, June 30th 2025, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 2nd time

24 days ago

on Wednesday, July 30th 2025, 6:30:00 pm
12.60%
Financial Progress

4th Expenditure
of ₹ 47804 (0.48 Lacs ) done.
Cummulative ₹ 53.28Lacs ( against 423.02Lacs )

22 days ago

on Friday, August 1st 2025, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 3rd time