Work Sanctioned
सडक सुरक्षा के अन्तर्गत जनपद चम्पावत म ेंककरालीगेट-ठूलीगाड-भैरव मंदिर मोटर मार्ग(राज्य मार्ग-108) एव ंसूखीढांग श्यामलाताल मोटर मार्ग।(राज्य मार्ग-110) मे अवशेष लम्बाई में क्रैश बैरियर लगाने का कार्य।
on Sunday, March 30th 2025, 6:30:00 pm
18.98%
Financial Progress
1st Expenditure
of ₹ 5425271 (54.25 Lacs ) done.
Cummulative ₹ 54.25Lacs ( against 285.89Lacs )
on Monday, April 7th 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Friday, May 30th 2025, 6:30:00 pm
20.71%
Financial Progress
2nd Expenditure
of ₹ 495600 (4.96 Lacs ) done.
Cummulative ₹ 59.21Lacs ( against 285.89Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
49.94%
Financial Progress
3rd Expenditure
of ₹ 8356135 (83.56 Lacs ) done.
Cummulative ₹ 142.77Lacs ( against 285.89Lacs )
on Monday, June 30th 2025, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 2nd time