9 years ago

on Sunday, June 26th 2016, 6:30:00 pm
Work Sanctioned
जनपद अल्मोड़ा के विधानसभा क्षेत्र जागेश्वर के अन्तर्गत चायखान-थुवासिमल मोटर मार्ग के कि0मी0 5.00 से उटेश्वर महादेव मन्दिर तक मोटर मार्ग का निर्माण कार्य। (दि्वतीय चरण)

9 years ago

on Friday, August 5th 2016, 6:30:00 pm

Technical Sanction
of ₹ 110.38 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4304/270c-01/16

9 years ago

on Tuesday, February 28th 2017, 6:30:00 pm
0.05%
Financial Progress

1st Expenditure
of ₹ 8500 (0.09 Lacs ) done.
Cummulative ₹ 0.09Lacs ( against 165.29Lacs )

8 years ago

on Sunday, April 30th 2017, 6:30:00 pm
8.58%
Financial Progress

2nd Expenditure
of ₹ 1409520 (14.10 Lacs ) done.
Cummulative ₹ 14.18Lacs ( against 165.29Lacs )

8 years ago

on Monday, July 31st 2017, 6:30:00 pm
16.67%
Financial Progress

3rd Expenditure
of ₹ 1337960 (13.38 Lacs ) done.
Cummulative ₹ 27.56Lacs ( against 165.29Lacs )

7 years ago

on Friday, August 31st 2018, 6:30:00 pm
25.89%
Financial Progress

4th Expenditure
of ₹ 1523118 (15.23 Lacs ) done.
Cummulative ₹ 42.79Lacs ( against 165.29Lacs )

7 years ago

on Monday, December 31st 2018, 6:30:00 pm
43.60%
Financial Progress

5th Expenditure
of ₹ 2927365 (29.27 Lacs ) done.
Cummulative ₹ 72.06Lacs ( against 165.29Lacs )

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
76.76%
Financial Progress

6th Expenditure
of ₹ 5480995 (54.81 Lacs ) done.
Cummulative ₹ 126.87Lacs ( against 165.29Lacs )

6 years ago

on Saturday, February 29th 2020, 6:30:00 pm
76.76%
Financial Progress

7th Expenditure
of ₹ 1008 (0.01 Lacs ) done.
Cummulative ₹ 126.88Lacs ( against 165.29Lacs )

5 years ago

on Wednesday, August 19th 2020, 6:30:00 pm

Technical Sanction
of ₹ 54.91 Lacs

2nd Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2413/270C-01/2020

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
46.74%
Financial Progress

8th Expenditure
of ₹ -4963297 (-49.63 Lacs ) done.
Cummulative ₹ 77.25Lacs ( against 165.29Lacs )

5 years ago

on Sunday, February 28th 2021, 6:30:00 pm
73.08%
Financial Progress

9th Expenditure
of ₹ 4354371 (43.54 Lacs ) done.
Cummulative ₹ 120.80Lacs ( against 165.29Lacs )

4 years ago

on Thursday, July 29th 2021, 6:30:00 pm
77.10%
Financial Progress

10th Expenditure
of ₹ 664473 (6.64 Lacs ) done.
Cummulative ₹ 127.44Lacs ( against 165.29Lacs )

4 years ago

on Friday, October 29th 2021, 6:30:00 pm
91.21%
Financial Progress

11th Expenditure
of ₹ 2331267 (23.31 Lacs ) done.
Cummulative ₹ 150.75Lacs ( against 165.29Lacs )

3 years ago

on Thursday, September 29th 2022, 6:30:00 pm
95.66%
Financial Progress

12th Expenditure
of ₹ 735999 (7.36 Lacs ) done.
Cummulative ₹ 158.11Lacs ( against 165.29Lacs )

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
100.07%
Financial Progress

13th Expenditure
of ₹ 729000 (7.29 Lacs ) done.
Cummulative ₹ 165.40Lacs ( against 165.29Lacs )

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
100.10%
Financial Progress

14th Expenditure
of ₹ 5098 (0.05 Lacs ) done.
Cummulative ₹ 165.45Lacs ( against 165.29Lacs )

7 days ago

on Wednesday, August 27th 2025, 6:30:00 pm
103.09%
Financial Progress

15th Expenditure
of ₹ 494918 (4.95 Lacs ) done.
Cummulative ₹ 170.40Lacs ( against 165.29Lacs )