Refresh data
Refresh data

7 years ago

on Thursday, February 28th 2019, 6:30:00 pm
0.09%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 109.11Lacs )

7 years ago

on Wednesday, March 6th 2019, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा सं0 504/2014 के अन्तर्गत जनपद अल्मोड़ा के विधानसभा क्षेत्र जागेश्वर के अन्तर्गत निसनी से कत्यारी मौअर मार्ग के नव निर्माण का कार्य (द्वितीय चरण)

6 years ago

on Wednesday, July 17th 2019, 6:30:00 pm

Technical Sanction
of ₹ 108.85 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2522/282C-01/

6 years ago

on Saturday, February 29th 2020, 6:30:00 pm
0.28%
Financial Progress

2nd Expenditure
of ₹ 20132 (0.20 Lacs ) done.
Cummulative ₹ 0.30Lacs ( against 109.11Lacs )

5 years ago

on Wednesday, September 30th 2020, 6:30:00 pm
9.67%
Financial Progress

3rd Expenditure
of ₹ 1024688 (10.25 Lacs ) done.
Cummulative ₹ 10.55Lacs ( against 109.11Lacs )

5 years ago

on Thursday, December 31st 2020, 6:30:00 pm
43.11%
Financial Progress

4th Expenditure
of ₹ 3648750 (36.49 Lacs ) done.
Cummulative ₹ 47.04Lacs ( against 109.11Lacs )

4 years ago

on Sunday, August 29th 2021, 6:30:00 pm
68.00%
Financial Progress

5th Expenditure
of ₹ 2716319 (27.16 Lacs ) done.
Cummulative ₹ 74.20Lacs ( against 109.11Lacs )

4 years ago

on Monday, February 21st 2022, 6:30:00 pm
69.37%
Financial Progress

6th Expenditure
of ₹ 149460 (1.49 Lacs ) done.
Cummulative ₹ 75.69Lacs ( against 109.11Lacs )

3 years ago

on Wednesday, March 30th 2022, 6:30:00 pm
70.35%
Financial Progress

7th Expenditure
of ₹ 106408 (1.06 Lacs ) done.
Cummulative ₹ 76.76Lacs ( against 109.11Lacs )

3 years ago

on Saturday, July 30th 2022, 6:30:00 pm
70.80%
Financial Progress

8th Expenditure
of ₹ 49560 (0.50 Lacs ) done.
Cummulative ₹ 77.25Lacs ( against 109.11Lacs )

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
79.72%
Financial Progress

9th Expenditure
of ₹ 973469 (9.73 Lacs ) done.
Cummulative ₹ 86.99Lacs ( against 109.11Lacs )

7 months ago

on Monday, January 27th 2025, 6:30:00 pm
88.22%
Financial Progress

10th Expenditure
of ₹ 926859 (9.27 Lacs ) done.
Cummulative ₹ 96.26Lacs ( against 109.11Lacs )

5 months ago

on Sunday, March 23rd 2025, 6:30:00 pm
89.02%
Financial Progress

11th Expenditure
of ₹ 87284 (0.87 Lacs ) done.
Cummulative ₹ 97.13Lacs ( against 109.11Lacs )

5 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
99.53%
Financial Progress

15th Expenditure
of ₹ 222492 (2.22 Lacs ) done.
Cummulative ₹ 108.59Lacs ( against 109.11Lacs )

5 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
97.49%
Financial Progress

14th Expenditure
of ₹ 237697 (2.38 Lacs ) done.
Cummulative ₹ 106.37Lacs ( against 109.11Lacs )

5 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
95.31%
Financial Progress

13th Expenditure
of ₹ 237697 (2.38 Lacs ) done.
Cummulative ₹ 103.99Lacs ( against 109.11Lacs )

5 months ago

on Tuesday, March 25th 2025, 6:30:00 pm
93.13%
Financial Progress

12th Expenditure
of ₹ 448400 (4.48 Lacs ) done.
Cummulative ₹ 101.61Lacs ( against 109.11Lacs )

5 months ago

on Thursday, March 27th 2025, 6:30:00 pm
100.00%
Financial Progress

18th Expenditure
of ₹ 28397 (0.28 Lacs ) done.
Cummulative ₹ 109.11Lacs ( against 109.11Lacs )

5 months ago

on Thursday, March 27th 2025, 6:30:00 pm
99.74%
Financial Progress

17th Expenditure
of ₹ 9440 (0.09 Lacs ) done.
Cummulative ₹ 108.83Lacs ( against 109.11Lacs )

5 months ago

on Thursday, March 27th 2025, 6:30:00 pm
99.65%
Financial Progress

16th Expenditure
of ₹ 13924 (0.14 Lacs ) done.
Cummulative ₹ 108.73Lacs ( against 109.11Lacs )