104 years ago

on Tuesday, June 21st 1921, 12:42:56 pm

Technical Sanction
of ₹ 10 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1316/11c

4 years ago

on Sunday, May 30th 2021, 6:30:00 pm
Work Sanctioned
लोक निर्माण विभाग के निरीक्षण भवन कटारमल में पहुॅच मार्ग का सुधारीकरण/डामरीकरण, स्कपर तथा नाली निर्माण कार्य

4 years ago

on Thursday, December 23rd 2021, 9:39:32 am
<span class="4">Picture Id:3873</span>
PWD Uttarakahnd
Photo (ID 3873) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Km 01
Remark : B/wall under construction

4 years ago

on Thursday, December 23rd 2021, 11:13:48 am
<span class="4">Picture Id:3874</span>
PWD Uttarakahnd
Photo (ID 3874) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Km 01
Remark : B/wall under construction

3 years ago

on Monday, May 30th 2022, 6:30:00 pm
14.76%
Financial Progress

1st Expenditure
of ₹ 147612 (1.48 Lacs ) done.
Cummulative ₹ 1.48Lacs ( against 10Lacs )

3 years ago

on Sunday, October 30th 2022, 6:30:00 pm
42.03%
Financial Progress

2nd Expenditure
of ₹ 272699 (2.73 Lacs ) done.
Cummulative ₹ 4.20Lacs ( against 10Lacs )

3 years ago

on Tuesday, November 29th 2022, 6:30:00 pm
81.70%
Financial Progress

3rd Expenditure
of ₹ 396658 (3.97 Lacs ) done.
Cummulative ₹ 8.17Lacs ( against 10Lacs )

a year ago

on Thursday, July 4th 2024, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 1st time

5 months ago

on Sunday, March 30th 2025, 6:30:00 pm
85.78%
Financial Progress

4th Expenditure
of ₹ 40792 (0.41 Lacs ) done.
Cummulative ₹ 8.58Lacs ( against 10Lacs )

5 months ago

on Saturday, April 19th 2025, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

AI layer

AI Road
AI Bridge
50 m
100 ft
Unavailable