3 years ago

on Tuesday, October 5th 2021, 6:30:00 pm
Work Sanctioned
आ0सी0एस0 योजनान्तर्गत जनपद अल्मोड़ा के स्थान फलसीमा-टाट्रिक में निर्मित हैलीपैड को हैलीपोर्ट में विकसित किये जाने का कार्य

2 years ago

on Tuesday, May 9th 2023, 6:30:00 pm
15.22%
Financial Progress

1st Expenditure
of ₹ 5672496 (56.72 Lacs ) done.
Cummulative ₹ 56.72Lacs ( against 372.68Lacs )

2 years ago

on Tuesday, May 9th 2023, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Wednesday, August 16th 2023, 6:30:00 pm
19.58%
Financial Progress

2nd Expenditure
of ₹ 1624328 (16.24 Lacs ) done.
Cummulative ₹ 72.97Lacs ( against 372.68Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
24.22%
Financial Progress

3rd Expenditure
of ₹ 1730852 (17.31 Lacs ) done.
Cummulative ₹ 90.28Lacs ( against 372.68Lacs )

a year ago

on Monday, January 22nd 2024, 6:30:00 pm
36.27%
Financial Progress

4th Expenditure
of ₹ 4488765 (44.89 Lacs ) done.
Cummulative ₹ 135.16Lacs ( against 372.68Lacs )

a year ago

on Tuesday, January 23rd 2024, 6:30:00 pm
95%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Tuesday, January 30th 2024, 6:30:00 pm
48.31%
Financial Progress

5th Expenditure
of ₹ 4488765 (44.89 Lacs ) done.
Cummulative ₹ 180.05Lacs ( against 372.68Lacs )

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
65.33%
Financial Progress

6th Expenditure
of ₹ 6341704 (63.42 Lacs ) done.
Cummulative ₹ 243.47Lacs ( against 372.68Lacs )

10 months ago

on Monday, April 22nd 2024, 6:30:00 pm
72.73%
Financial Progress

7th Expenditure
of ₹ 2758539 (27.59 Lacs ) done.
Cummulative ₹ 271.05Lacs ( against 372.68Lacs )

10 months ago

on Monday, April 29th 2024, 6:30:00 pm
82.29%
Financial Progress

8th Expenditure
of ₹ 3561000 (35.61 Lacs ) done.
Cummulative ₹ 306.66Lacs ( against 372.68Lacs )

10 months ago

on Tuesday, May 7th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

7 months ago

on Wednesday, July 24th 2024, 6:30:00 pm
88.99%
Financial Progress

9th Expenditure
of ₹ 2500000 (25.00 Lacs ) done.
Cummulative ₹ 331.66Lacs ( against 372.68Lacs )

5 months ago

on Sunday, September 29th 2024, 6:30:00 pm
110.18%
Financial Progress

10th Expenditure
of ₹ 7896838 (78.97 Lacs ) done.
Cummulative ₹ 410.63Lacs ( against 372.68Lacs )