on Monday, September 13th 2021, 6:30:00 pm
Work Sanctioned
विधानसभा क्षेत्र सोमेश्वर में शीतलाखेत-काकड़ीघाट (मटेला) मे ंसुधारीकरण एवं डामरीकरण का कार्य
on Friday, December 17th 2021, 12:51:12 pm
Technical Sanction
of ₹ 334.03 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4499/535YATA-A/2021
on Wednesday, August 24th 2022, 7:15:32 am
PWD UttarakahndPhoto (ID 7353) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 0.00
Remark : Starting point of Road
on Wednesday, August 24th 2022, 7:23:46 am
PWD UttarakahndPhoto (ID 7354) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 0.00
Remark : Starting point
on Wednesday, August 24th 2022, 7:42:46 am
PWD UttarakahndPhoto (ID 7355) from Site Received
Uploader : Pradeep Kumar Joshi, Additional Assistant Engineer Civil ,PD Almora
Landmark : 0.00
Remark : Starting point
on Wednesday, August 24th 2022, 8:16:54 am
PWD UttarakahndPhoto (ID 7358) from Site Received
Uploader : Pradeep Kumar Joshi, Additional Assistant Engineer Civil ,PD Almora
Landmark : 2.800
Remark : Retaining wall
on Saturday, October 29th 2022, 6:30:00 pm
17.37%
Financial Progress
1st Expenditure
of ₹ 5802166 (58.02 Lacs ) done.
Cummulative ₹ 58.02Lacs ( against 334.03Lacs )
on Tuesday, January 31st 2023, 6:30:00 pm
37.61%
Financial Progress
2nd Expenditure
of ₹ 6761950 (67.62 Lacs ) done.
Cummulative ₹ 125.64Lacs ( against 334.03Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
46.96%
Financial Progress
3rd Expenditure
of ₹ 3121154 (31.21 Lacs ) done.
Cummulative ₹ 156.85Lacs ( against 334.03Lacs )
on Wednesday, May 10th 2023, 6:30:00 pm
40%
Physical Progress
Physical Progress Reported at 1st time
on Monday, May 15th 2023, 6:27:44 am
PWD UttarakahndPhoto (ID 19604) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 0/8
Remark : Damrikaran
on Monday, June 19th 2023, 6:30:00 pm
74.28%
Financial Progress
4th Expenditure
of ₹ 9125136 (91.25 Lacs ) done.
Cummulative ₹ 248.10Lacs ( against 334.03Lacs )
on Thursday, October 5th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, November 29th 2023, 6:30:00 pm
90.16%
Financial Progress
5th Expenditure
of ₹ 5307190 (53.07 Lacs ) done.
Cummulative ₹ 301.18Lacs ( against 334.03Lacs )
on Monday, January 29th 2024, 6:30:00 pm
95%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, February 18th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Wednesday, March 27th 2024, 5:37:50 am
PWD UttarakahndPhoto (ID 37171) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 0/39
Remark : Inspection of road by CE Sir.
on Wednesday, March 27th 2024, 6:40:26 am
PWD UttarakahndPhoto (ID 37172) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 1/24
Remark : Inspection of road by CE Sir.
on Wednesday, March 27th 2024, 6:42:54 am
PWD UttarakahndPhoto (ID 37173) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 1/24
Remark : Inspection of road by CE Sir.
on Wednesday, March 27th 2024, 7:08:55 am
PWD UttarakahndPhoto (ID 37174) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 2/22
Remark : Inspection of road by CE Sir.
on Wednesday, March 27th 2024, 7:15:01 am
PWD UttarakahndPhoto (ID 37175) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 2/28
Remark : Scupper check by CE Sir.
on Wednesday, March 27th 2024, 7:30:17 am
PWD UttarakahndPhoto (ID 37176) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : 2/30
Remark : Inspection of road by CE Sir.
on Wednesday, March 27th 2024, 8:01:28 am
PWD UttarakahndPhoto (ID 37177) from Site Received
Uploader : Kamal Goyal, Assistant Engineer Civil ,PD Almora
Landmark : Km. 4 hm 2-4
Remark : Checking in road by CE Sir.
on Thursday, May 30th 2024, 6:30:00 pm
92.06%
Financial Progress
6th Expenditure
of ₹ 633240 (6.33 Lacs ) done.
Cummulative ₹ 307.51Lacs ( against 334.03Lacs )
on Sunday, February 23rd 2025, 6:30:00 pm
93.03%
Financial Progress
7th Expenditure
of ₹ 323915 (3.24 Lacs ) done.
Cummulative ₹ 310.75Lacs ( against 334.03Lacs )