3 years ago

on Friday, October 28th 2022, 6:30:00 pm
Work Sanctioned
विधानसभा क्षेत्र अल्मोड़ा के फलसीमा-टाट्रिक मोटर मार्ग के कि0मी0 4 है0मी0 4-6 से आगे अवशेष 700 मीटर लम्बाई में डामरीकरण/सुधारीकरण का कार्य

3 years ago

on Saturday, December 31st 2022, 6:30:00 pm
30.04%
Financial Progress

1st Expenditure
of ₹ 1587446 (15.87 Lacs ) done.
Cummulative ₹ 15.87Lacs ( against 52.84Lacs )

3 years ago

on Tuesday, February 28th 2023, 6:30:00 pm
54.07%
Financial Progress

2nd Expenditure
of ₹ 1269587 (12.70 Lacs ) done.
Cummulative ₹ 28.57Lacs ( against 52.84Lacs )

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Monday, July 17th 2023, 6:30:00 pm
75.08%
Financial Progress

3rd Expenditure
of ₹ 1110026 (11.10 Lacs ) done.
Cummulative ₹ 39.67Lacs ( against 52.84Lacs )

2 years ago

on Tuesday, February 20th 2024, 6:30:00 pm
75.42%
Financial Progress

4th Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 39.85Lacs ( against 52.84Lacs )

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
76.48%
Financial Progress

5th Expenditure
of ₹ 56237 (0.56 Lacs ) done.
Cummulative ₹ 40.41Lacs ( against 52.84Lacs )

a year ago

on Thursday, May 30th 2024, 6:30:00 pm
78.60%
Financial Progress

6th Expenditure
of ₹ 112000 (1.12 Lacs ) done.
Cummulative ₹ 41.53Lacs ( against 52.84Lacs )

a year ago

on Friday, August 30th 2024, 6:30:00 pm
87.48%
Financial Progress

7th Expenditure
of ₹ 468928 (4.69 Lacs ) done.
Cummulative ₹ 46.22Lacs ( against 52.84Lacs )

7 months ago

on Sunday, January 26th 2025, 6:30:00 pm
87.76%
Financial Progress

8th Expenditure
of ₹ 14833 (0.15 Lacs ) done.
Cummulative ₹ 46.37Lacs ( against 52.84Lacs )

7 months ago

on Sunday, January 26th 2025, 6:30:00 pm
87.95%
Financial Progress

9th Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 46.47Lacs ( against 52.84Lacs )

7 months ago

on Monday, January 27th 2025, 6:30:00 pm
88.21%
Financial Progress

10th Expenditure
of ₹ 13728 (0.14 Lacs ) done.
Cummulative ₹ 46.61Lacs ( against 52.84Lacs )