2 years ago

on Monday, February 13th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्य मंत्री घोषणा सं0 508ध्2014 के अन्तर्गत जनपद अल्मेड़ा के विधानसभा क्षेत्र जागेश्वर में पूनागढ़-नाटाडोल मोटर मार्ग के दयाल बैण्ड से तल्ला गांव तक मोटर मार्ग का नव निर्माण कार्य (द्वितीय चरण स्टेज-।)

2 years ago

on Thursday, March 30th 2023, 6:30:00 pm
0.11%
Financial Progress

1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 90.15Lacs )

a year ago

on Tuesday, September 19th 2023, 6:30:00 pm
0.26%
Financial Progress

2nd Expenditure
of ₹ 13760 (0.14 Lacs ) done.
Cummulative ₹ 0.24Lacs ( against 90.15Lacs )

a year ago

on Wednesday, November 29th 2023, 6:30:00 pm
26.97%
Financial Progress

3rd Expenditure
of ₹ 2407200 (24.07 Lacs ) done.
Cummulative ₹ 24.31Lacs ( against 90.15Lacs )

a year ago

on Wednesday, February 28th 2024, 6:30:00 pm
38.37%
Financial Progress

4th Expenditure
of ₹ 1028452 (10.28 Lacs ) done.
Cummulative ₹ 34.59Lacs ( against 90.15Lacs )

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
44.96%
Financial Progress

5th Expenditure
of ₹ 593733 (5.94 Lacs ) done.
Cummulative ₹ 40.53Lacs ( against 90.15Lacs )

10 months ago

on Thursday, May 9th 2024, 6:30:00 pm
45.30%
Financial Progress

6th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 40.84Lacs ( against 90.15Lacs )

9 months ago

on Sunday, May 26th 2024, 6:30:00 pm
46.34%
Financial Progress

10th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 41.77Lacs ( against 90.15Lacs )

9 months ago

on Sunday, May 26th 2024, 6:30:00 pm
45.99%
Financial Progress

9th Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 41.46Lacs ( against 90.15Lacs )

9 months ago

on Sunday, May 26th 2024, 6:30:00 pm
45.65%
Financial Progress

8th Expenditure
of ₹ 9000 (0.09 Lacs ) done.
Cummulative ₹ 41.15Lacs ( against 90.15Lacs )

9 months ago

on Sunday, May 26th 2024, 6:30:00 pm
45.55%
Financial Progress

7th Expenditure
of ₹ 22000 (0.22 Lacs ) done.
Cummulative ₹ 41.06Lacs ( against 90.15Lacs )

9 months ago

on Thursday, May 30th 2024, 6:30:00 pm
48.12%
Financial Progress

11th Expenditure
of ₹ 160998 (1.61 Lacs ) done.
Cummulative ₹ 43.38Lacs ( against 90.15Lacs )

8 months ago

on Tuesday, July 2nd 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

6 months ago

on Friday, August 30th 2024, 6:30:00 pm
48.22%
Financial Progress

12th Expenditure
of ₹ 8766 (0.09 Lacs ) done.
Cummulative ₹ 43.47Lacs ( against 90.15Lacs )

5 months ago

on Monday, September 30th 2024, 6:30:00 pm
60.41%
Financial Progress

13th Expenditure
of ₹ 1098859 (10.99 Lacs ) done.
Cummulative ₹ 54.46Lacs ( against 90.15Lacs )

4 months ago

on Tuesday, October 29th 2024, 6:30:00 pm
60.41%
Financial Progress

14th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 54.46Lacs ( against 90.15Lacs )

3 months ago

on Friday, November 29th 2024, 6:30:00 pm
60.41%
Financial Progress

15th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 54.46Lacs ( against 90.15Lacs )