Technical Sanction
of ₹ 30 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 2868/11c
on Tuesday, September 27th 2022, 6:30:00 pm
Work Sanctioned
राष्ट्रीय राजमार्ग से विकास भवन होते हुए न्यू कलैक्ट्रेट तक मोटर मार्ग में क्षतिग्रस्त दीवार का पुनः निर्माण, क्रैश बैरियर, पैरापिट व पटरी का निर्माण कार्य
on Tuesday, February 28th 2023, 6:30:00 pm
60.48%
Financial Progress
1st Expenditure
of ₹ 1814252 (18.14 Lacs ) done.
Cummulative ₹ 18.14Lacs ( against 30Lacs )
on Friday, March 31st 2023, 6:30:00 pm
77.65%
Financial Progress
2nd Expenditure
of ₹ 515258 (5.15 Lacs ) done.
Cummulative ₹ 23.30Lacs ( against 30Lacs )
on Tuesday, April 11th 2023, 6:30:00 pm
94.73%
Financial Progress
3rd Expenditure
of ₹ 512258 (5.12 Lacs ) done.
Cummulative ₹ 28.42Lacs ( against 30Lacs )
on Wednesday, May 3rd 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, February 28th 2024, 6:30:00 pm
97.82%
Financial Progress
4th Expenditure
of ₹ 92925 (0.93 Lacs ) done.
Cummulative ₹ 29.35Lacs ( against 30Lacs )
on Thursday, February 29th 2024, 6:30:00 pm
99.99%
Financial Progress
5th Expenditure
of ₹ 65000 (0.65 Lacs ) done.
Cummulative ₹ 30.00Lacs ( against 30Lacs )
on Thursday, July 4th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time