Technical Sanction
of ₹ 5 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 904/11c
on Tuesday, September 27th 2022, 6:30:00 pm
Work Sanctioned
ग्राम सभा माल में लता आर्या के घर के समीप नाला निर्माण
on Friday, May 5th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Friday, May 12th 2023, 6:30:00 pm
45.02%
Financial Progress
1st Expenditure
of ₹ 225079 (2.25 Lacs ) done.
Cummulative ₹ 2.25Lacs ( against 5Lacs )
on Thursday, June 15th 2023, 6:30:00 pm
70.44%
Financial Progress
2nd Expenditure
of ₹ 127143 (1.27 Lacs ) done.
Cummulative ₹ 3.52Lacs ( against 5Lacs )
on Thursday, July 4th 2024, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 2nd time