3 years ago

on Tuesday, September 27th 2022, 6:30:00 pm
Work Sanctioned
आर0टी0ओ0 कार्यालय पहुंच मार्ग में मार्ग का सुधारीकरण कार्य

3 years ago

on Sunday, October 23rd 2022, 10:51:35 am

Technical Sanction
of ₹ 8 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 900/11c

2 years ago

on Sunday, April 9th 2023, 6:30:00 pm
74.33%
Financial Progress

1st Expenditure
of ₹ 594678 (5.95 Lacs ) done.
Cummulative ₹ 5.95Lacs ( against 8Lacs )

2 years ago

on Saturday, February 24th 2024, 6:30:00 pm
99.23%
Financial Progress

2nd Expenditure
of ₹ 199193 (1.99 Lacs ) done.
Cummulative ₹ 7.94Lacs ( against 8Lacs )

a year ago

on Thursday, April 11th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 1st time

a year ago

on Friday, August 30th 2024, 6:30:00 pm
124.86%
Financial Progress

3rd Expenditure
of ₹ 205000 (2.05 Lacs ) done.
Cummulative ₹ 9.99Lacs ( against 8Lacs )