Work Sanctioned
शीतालाखेत कठपुड़िया मोटर मार्ग से बटगल भट्ट (मल्ला) तक मोटर मार्ग

17 years ago

on Saturday, February 28th 2009, 6:30:00 pm
0.32%
Financial Progress

1st Expenditure
of ₹ 45000 (0.45 Lacs ) done.
Cummulative ₹ 0.45Lacs ( against 140Lacs )

16 years ago

on Sunday, January 31st 2010, 6:30:00 pm
0.45%
Financial Progress

2nd Expenditure
of ₹ 18000 (0.18 Lacs ) done.
Cummulative ₹ 0.63Lacs ( against 140Lacs )

15 years ago

on Monday, May 31st 2010, 6:30:00 pm
0.54%
Financial Progress

3rd Expenditure
of ₹ 12000 (0.12 Lacs ) done.
Cummulative ₹ 0.75Lacs ( against 140Lacs )

15 years ago

on Monday, February 28th 2011, 6:30:00 pm
0.57%
Financial Progress

4th Expenditure
of ₹ 5000 (0.05 Lacs ) done.
Cummulative ₹ 0.80Lacs ( against 140Lacs )

10 years ago

on Saturday, October 31st 2015, 6:30:00 pm
0.83%
Financial Progress

5th Expenditure
of ₹ 36895 (0.37 Lacs ) done.
Cummulative ₹ 1.17Lacs ( against 140Lacs )

10 years ago

on Monday, November 30th 2015, 6:30:00 pm
1.00%
Financial Progress

6th Expenditure
of ₹ 23200 (0.23 Lacs ) done.
Cummulative ₹ 1.40Lacs ( against 140Lacs )

9 years ago

on Monday, August 15th 2016, 6:30:00 pm

Technical Sanction
of ₹ 140 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4317/234C-01/16

9 years ago

on Friday, September 30th 2016, 6:30:00 pm
1.36%
Financial Progress

7th Expenditure
of ₹ 50994 (0.51 Lacs ) done.
Cummulative ₹ 1.91Lacs ( against 140Lacs )

7 years ago

on Monday, April 30th 2018, 6:30:00 pm
3.72%
Financial Progress

8th Expenditure
of ₹ 329774 (3.30 Lacs ) done.
Cummulative ₹ 5.21Lacs ( against 140Lacs )

7 years ago

on Tuesday, July 31st 2018, 6:30:00 pm
10.78%
Financial Progress

9th Expenditure
of ₹ 987840 (9.88 Lacs ) done.
Cummulative ₹ 15.09Lacs ( against 140Lacs )

6 years ago

on Thursday, October 31st 2019, 6:30:00 pm
10.91%
Financial Progress

10th Expenditure
of ₹ 18221 (0.18 Lacs ) done.
Cummulative ₹ 15.27Lacs ( against 140Lacs )

6 years ago

on Saturday, November 30th 2019, 6:30:00 pm
15.61%
Financial Progress

11th Expenditure
of ₹ 657905 (6.58 Lacs ) done.
Cummulative ₹ 21.85Lacs ( against 140Lacs )

6 years ago

on Saturday, February 29th 2020, 6:30:00 pm
15.79%
Financial Progress

12th Expenditure
of ₹ 25170 (0.25 Lacs ) done.
Cummulative ₹ 22.10Lacs ( against 140Lacs )

4 years ago

on Wednesday, September 29th 2021, 6:30:00 pm
35.35%
Financial Progress

13th Expenditure
of ₹ 2739300 (27.39 Lacs ) done.
Cummulative ₹ 49.49Lacs ( against 140Lacs )

3 years ago

on Friday, September 30th 2022, 6:30:00 pm
39.64%
Financial Progress

14th Expenditure
of ₹ 600000 (6.00 Lacs ) done.
Cummulative ₹ 55.49Lacs ( against 140Lacs )

3 years ago

on Tuesday, January 31st 2023, 6:30:00 pm
40.85%
Financial Progress

15th Expenditure
of ₹ 170084 (1.70 Lacs ) done.
Cummulative ₹ 57.19Lacs ( against 140Lacs )

2 years ago

on Wednesday, May 10th 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Sunday, December 17th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 2nd time

a year ago

on Wednesday, March 27th 2024, 6:30:00 pm
58.63%
Financial Progress

16th Expenditure
of ₹ 2489162 (24.89 Lacs ) done.
Cummulative ₹ 82.09Lacs ( against 140Lacs )

a year ago

on Friday, July 5th 2024, 6:30:00 pm
64.62%
Financial Progress

17th Expenditure
of ₹ 838507 (8.39 Lacs ) done.
Cummulative ₹ 90.47Lacs ( against 140Lacs )

a year ago

on Tuesday, July 30th 2024, 6:30:00 pm
75.37%
Financial Progress

19th Expenditure
of ₹ 1504500 (15.04 Lacs ) done.
Cummulative ₹ 105.52Lacs ( against 140Lacs )

a year ago

on Tuesday, July 30th 2024, 6:30:00 pm
64.62%
Financial Progress

18th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 90.47Lacs ( against 140Lacs )

a year ago

on Monday, September 30th 2024, 6:30:00 pm
76.04%
Financial Progress

20th Expenditure
of ₹ 93529 (0.94 Lacs ) done.
Cummulative ₹ 106.45Lacs ( against 140Lacs )

10 months ago

on Tuesday, October 29th 2024, 6:30:00 pm
76.04%
Financial Progress

21st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 106.45Lacs ( against 140Lacs )