Refresh data
on Tuesday, November 16th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद पिथौरागढ़ के विधानसभा गंगोलीहाट के अन्तर्गत डंगोली सैलानी दाड़िमखेत धरमघर कोटमन्या पाॅखू थल सातसिलिंग मोटर मार्ग (एस0एच0-60) में सुधारीकरण एवं हाॅटमिक्स का कार्य (कोटमन्या से बरड़बैण्ड तक का प्रभाग) किमी0 112.00 से 114.00 (विस्तृत आगणन)
on Thursday, January 6th 2022, 11:07:49 am
Technical Sanction
of ₹ 340.85 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE Letter No. 50/04 yata-a/2021 dt. 06.01.2022
on Friday, March 10th 2023, 6:15:14 am
PWD UttarakahndPhoto (ID 19543) from Site Received
Uploader : Aditya Kumar Patni, JE Civil (Samvida) ,TD Berinaag
Landmark : KM112
Remark : BM work in progress at km 112 SH 60 kotmanya pankhu
on Friday, March 24th 2023, 6:30:00 pm
17.08%
Financial Progress
1st Expenditure
of ₹ 6068637 (60.69 Lacs ) done.
Cummulative ₹ 60.69Lacs ( against 355.39Lacs )
on Wednesday, April 5th 2023, 3:17:30 am
PWD UttarakahndPhoto (ID 19096) from Site Received
Uploader : Sanjeev Bhatt, Assistant Engineer Civil ,PD Champawat
Landmark : Ch 113.825
Remark : Consolidation of W.M.M. Work
on Wednesday, April 5th 2023, 3:39:53 am
PWD UttarakahndPhoto (ID 19097) from Site Received
Uploader : Sanjeev Bhatt, Assistant Engineer Civil ,PD Champawat
Landmark : Ch 113.850
Remark : Consolidation of W.M.M. Work
on Monday, June 5th 2023, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, June 11th 2023, 6:30:00 pm
36.77%
Financial Progress
2nd Expenditure
of ₹ 7000000 (70.00 Lacs ) done.
Cummulative ₹ 130.69Lacs ( against 355.39Lacs )
on Monday, June 19th 2023, 6:30:00 pm
36.78%
Financial Progress
3rd Expenditure
of ₹ 2100 (0.02 Lacs ) done.
Cummulative ₹ 130.71Lacs ( against 355.39Lacs )
on Sunday, July 2nd 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, August 22nd 2023, 6:30:00 pm
36.85%
Financial Progress
4th Expenditure
of ₹ 24255 (0.24 Lacs ) done.
Cummulative ₹ 130.95Lacs ( against 355.39Lacs )
on Thursday, August 24th 2023, 6:30:00 pm
74.46%
Financial Progress
5th Expenditure
of ₹ 13365581 (133.66 Lacs ) done.
Cummulative ₹ 264.61Lacs ( against 355.39Lacs )
on Wednesday, September 13th 2023, 12:32:12 am
PWD UttarakahndPhoto (ID 23945) from Site Received
Uploader : Aditya Kumar Patni, JE Civil (Samvida) ,TD Berinaag
Landmark : KM 1
Remark : BM SDBC work
on Wednesday, September 13th 2023, 12:43:02 am
PWD UttarakahndPhoto (ID 23946) from Site Received
Uploader : Aditya Kumar Patni, JE Civil (Samvida) ,TD Berinaag
Landmark : KM 2
Remark : BM work
on Wednesday, September 13th 2023, 12:45:18 am
PWD UttarakahndPhoto (ID 23947) from Site Received
Uploader : Aditya Kumar Patni, JE Civil (Samvida) ,TD Berinaag
Landmark : KM 2
Remark : BM SDBC work
on Sunday, September 24th 2023, 6:30:00 pm
77.22%
Financial Progress
6th Expenditure
of ₹ 983702 (9.84 Lacs ) done.
Cummulative ₹ 274.44Lacs ( against 355.39Lacs )
on Monday, September 25th 2023, 6:30:00 pm
83.84%
Financial Progress
7th Expenditure
of ₹ 2350228 (23.50 Lacs ) done.
Cummulative ₹ 297.95Lacs ( against 355.39Lacs )
on Tuesday, September 26th 2023, 6:30:00 pm
83.90%
Financial Progress
8th Expenditure
of ₹ 23760 (0.24 Lacs ) done.
Cummulative ₹ 298.18Lacs ( against 355.39Lacs )
on Wednesday, October 25th 2023, 6:30:00 pm
84.03%
Financial Progress
9th Expenditure
of ₹ 46930 (0.47 Lacs ) done.
Cummulative ₹ 298.65Lacs ( against 355.39Lacs )
on Friday, December 1st 2023, 6:30:00 pm
84.03%
Financial Progress
10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 298.65Lacs ( against 355.39Lacs )
on Friday, December 1st 2023, 6:30:00 pm
84.03%
Financial Progress
11th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 298.65Lacs ( against 355.39Lacs )
on Monday, January 22nd 2024, 6:30:00 pm
84.58%
Financial Progress
12th Expenditure
of ₹ 192070 (1.92 Lacs ) done.
Cummulative ₹ 300.57Lacs ( against 355.39Lacs )
on Tuesday, January 30th 2024, 6:30:00 pm
85.05%
Financial Progress
14th Expenditure
of ₹ 85138 (0.85 Lacs ) done.
Cummulative ₹ 302.28Lacs ( against 355.39Lacs )
on Tuesday, January 30th 2024, 6:30:00 pm
84.81%
Financial Progress
13th Expenditure
of ₹ 85138 (0.85 Lacs ) done.
Cummulative ₹ 301.42Lacs ( against 355.39Lacs )
on Wednesday, February 14th 2024, 6:30:00 pm
91.69%
Financial Progress
15th Expenditure
of ₹ 2358546 (23.59 Lacs ) done.
Cummulative ₹ 325.86Lacs ( against 355.39Lacs )
on Tuesday, February 20th 2024, 6:30:00 pm
91.90%
Financial Progress
16th Expenditure
of ₹ 74366 (0.74 Lacs ) done.
Cummulative ₹ 326.60Lacs ( against 355.39Lacs )
on Tuesday, March 12th 2024, 6:30:00 pm
96.71%
Financial Progress
17th Expenditure
of ₹ 1709549 (17.10 Lacs ) done.
Cummulative ₹ 343.70Lacs ( against 355.39Lacs )
on Monday, March 18th 2024, 6:30:00 pm
96.72%
Financial Progress
18th Expenditure
of ₹ 3000 (0.03 Lacs ) done.
Cummulative ₹ 343.73Lacs ( against 355.39Lacs )
on Thursday, January 9th 2025, 6:30:00 pm
97.18%
Financial Progress
19th Expenditure
of ₹ 163359 (1.63 Lacs ) done.
Cummulative ₹ 345.36Lacs ( against 355.39Lacs )