on Wednesday, March 19th 2025, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद नैनीताल के विधान सभा क्षेत्र-लालकुआं के उदयपुर रैक्वाल, सीतापुर, जीतपुर रैक्वाल, एवं कल्याणपुर गौलापार में पी0सी0 द्वारा मार्ग का नवनिर्माण कार्य।
on Saturday, March 29th 2025, 6:30:00 pm
0.12%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 80.88Lacs )
on Sunday, April 27th 2025, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, July 16th 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, July 24th 2025, 6:30:00 pm
11.72%
Financial Progress
2nd Expenditure
of ₹ 938219 (9.38 Lacs ) done.
Cummulative ₹ 9.48Lacs ( against 80.88Lacs )
on Tuesday, July 29th 2025, 6:30:00 pm
12.11%
Financial Progress
3rd Expenditure
of ₹ 31000 (0.31 Lacs ) done.
Cummulative ₹ 9.79Lacs ( against 80.88Lacs )
on Tuesday, August 19th 2025, 6:30:00 pm
13.04%
Financial Progress
4th Expenditure
of ₹ 75225 (0.75 Lacs ) done.
Cummulative ₹ 10.54Lacs ( against 80.88Lacs )