9 months ago

on Monday, August 5th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद ऊधमसिंह नगर के विधानसभा क्षेत्र रूद्रपुर के अन्तर्गत एन0एच0-09 (बगवाड़ा) से तीन पानी डैम तक मार्ग के पुनः निर्माण कार्य के अन्तर्गत सतह सुधार एवं आबादी क्षेत्र में इण्टर लाॅकिंग टाईल्स लगाने का कार्य। (विस्तृत आगणन)

5 months ago

on Tuesday, December 17th 2024, 6:30:00 pm
24.71%
Financial Progress

1st Expenditure
of ₹ 5343453 (53.43 Lacs ) done.
Cummulative ₹ 53.43Lacs ( against 216.29Lacs )

5 months ago

on Thursday, December 26th 2024, 6:30:00 pm
43.60%
Financial Progress

2nd Expenditure
of ₹ 4087142 (40.87 Lacs ) done.
Cummulative ₹ 94.31Lacs ( against 216.29Lacs )

4 months ago

on Monday, December 30th 2024, 6:30:00 pm
80%

Physical Progress
Physical Progress Reported at 1st time

4 months ago

on Tuesday, December 31st 2024, 6:30:00 pm
50.97%
Financial Progress

3rd Expenditure
of ₹ 1594000 (15.94 Lacs ) done.
Cummulative ₹ 110.25Lacs ( against 216.29Lacs )

4 months ago

on Friday, January 24th 2025, 5:46:46 am
<span class="4">Picture Id:63308</span>
PWD Uttarakahnd
Photo (ID 63308) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : Km 2 Near Stone Ridge public school
Remark : Compaction of WBM for Interlocking Tiles

3 months ago

on Friday, February 7th 2025, 1:25:24 am
<span class="4">Picture Id:64162</span>
PWD Uttarakahnd
Photo (ID 64162) from Site Received
Uploader : Prakash Chandra Pant, Additional Assistant Engineer Civil ,PD Rudrapur
Landmark : 0.575
Remark : Core cutting of BM/SDBC

3 months ago

on Sunday, February 16th 2025, 6:30:00 pm
51.04%
Financial Progress

4th Expenditure
of ₹ 14010 (0.14 Lacs ) done.
Cummulative ₹ 110.39Lacs ( against 216.29Lacs )

3 months ago

on Sunday, February 16th 2025, 6:30:00 pm
51.24%
Financial Progress

5th Expenditure
of ₹ 45174 (0.45 Lacs ) done.
Cummulative ₹ 110.84Lacs ( against 216.29Lacs )

3 months ago

on Sunday, February 16th 2025, 6:30:00 pm
51.41%
Financial Progress

6th Expenditure
of ₹ 36540 (0.37 Lacs ) done.
Cummulative ₹ 111.20Lacs ( against 216.29Lacs )

2 months ago

on Thursday, February 27th 2025, 6:30:00 pm
59.17%
Financial Progress

7th Expenditure
of ₹ 1678539 (16.79 Lacs ) done.
Cummulative ₹ 127.99Lacs ( against 216.29Lacs )

2 months ago

on Tuesday, March 11th 2025, 6:30:00 pm
59.86%
Financial Progress

8th Expenditure
of ₹ 149329 (1.49 Lacs ) done.
Cummulative ₹ 129.48Lacs ( against 216.29Lacs )

2 months ago

on Monday, March 17th 2025, 6:30:00 pm
60.40%
Financial Progress

9th Expenditure
of ₹ 115640 (1.16 Lacs ) done.
Cummulative ₹ 130.64Lacs ( against 216.29Lacs )

7 days ago

on Monday, May 5th 2025, 6:30:00 pm
90%

Physical Progress
Physical Progress Reported at 2nd time

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors