Work Sanctioned
राज्य योजना के अन्तर्गत जनपद ऊधमसिंह नगर के विधानसभा क्षेत्र किच्छा के पनचक्की फार्म में नहर के साथ सुनहरा मार्ग तक मार्ग का पी0सी0 द्वारा पुनःनिर्माण का कार्य। (विस्तृत आगणन)
on Tuesday, January 28th 2025, 6:30:00 pm
36.16%
Financial Progress
1st Expenditure
of ₹ 2520605 (25.21 Lacs ) done.
Cummulative ₹ 25.21Lacs ( against 69.7Lacs )
on Friday, February 14th 2025, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, March 6th 2025, 3:12:16 am
PWD UttarakahndPhoto (ID 65472) from Site Received
Uploader : Yogesh Tatrari, Junior Engineer Civil ,PD Rudrapur
Landmark : K 2 hm 9-10
Remark : Pc Work
on Thursday, March 6th 2025, 3:16:11 am
PWD UttarakahndPhoto (ID 65473) from Site Received
Uploader : Yogesh Tatrari, Junior Engineer Civil ,PD Rudrapur
Landmark : Km 2 hm 5-6
Remark : Pc Work in progress
on Thursday, March 6th 2025, 3:42:10 am
PWD UttarakahndPhoto (ID 65477) from Site Received
Uploader : Yogesh Tatrari, Junior Engineer Civil ,PD Rudrapur
Landmark : Km1hm 0-1
Remark : Up to Wbm G3 work completed
on Thursday, March 6th 2025, 3:45:57 am
PWD UttarakahndPhoto (ID 65478) from Site Received
Uploader : Yogesh Tatrari, Junior Engineer Civil ,PD Rudrapur
Landmark : Km1 hm 2-3
Remark : Up to Wbm G 3 completed
on Tuesday, April 8th 2025, 6:30:00 pm
90%
Physical Progress
Physical Progress Reported at 2nd time