on Thursday, September 19th 2024, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत विधान सभा क्षेत्र सितारगंज के अन्तर्गत ग्राम बरूआबाग में प्राईमरी स्कूल टंकी से ग्राम मझरा में गोतम की दुकान तक मार्ग का निर्माण कार्य।
on Friday, December 6th 2024, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Monday, January 6th 2025, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, February 11th 2025, 6:30:00 pm
33.95%
Financial Progress
1st Expenditure
of ₹ 2521140 (25.21 Lacs ) done.
Cummulative ₹ 25.21Lacs ( against 74.25Lacs )
on Friday, February 14th 2025, 6:30:00 pm
65.74%
Financial Progress
2nd Expenditure
of ₹ 2360000 (23.60 Lacs ) done.
Cummulative ₹ 48.81Lacs ( against 74.25Lacs )
on Friday, February 14th 2025, 6:30:00 pm
33.95%
Financial Progress
3rd Expenditure
of ₹ -2360000 (-23.60 Lacs ) done.
Cummulative ₹ 25.21Lacs ( against 74.25Lacs )
on Monday, March 3rd 2025, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, March 11th 2025, 6:30:00 pm
34.62%
Financial Progress
4th Expenditure
of ₹ 49224 (0.49 Lacs ) done.
Cummulative ₹ 25.70Lacs ( against 74.25Lacs )
on Sunday, April 6th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Monday, April 7th 2025, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 5th time
on Sunday, June 8th 2025, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 6th time
on Sunday, June 29th 2025, 6:30:00 pm
63.77%
Financial Progress
5th Expenditure
of ₹ 2164574 (21.65 Lacs ) done.
Cummulative ₹ 47.35Lacs ( against 74.25Lacs )
on Tuesday, July 8th 2025, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 7th time