on Thursday, January 6th 2022, 6:30:00 pm
Work Sanctioned
मा0मुख्यमंत्री घोषणा संख्या 348/2021 जनपद उधमसिंह नगर के विधानसभा क्षेत्र खटीमा के अन्तर्गत नदन्ना से गौहर मोटर मार्ग का नवीनीकरण का कार्य।

4 years ago

on Friday, January 7th 2022, 3:19:06 am

Technical Sanction
of ₹ 88.82 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1165/EE

3 years ago

on Wednesday, November 9th 2022, 2:59:44 am
<span class="4">Picture Id:9067</span>
PWD Uttarakahnd
Photo (ID 9067) from Site Received
Uploader : Gopal Giri Goswami, Assistant Engineer Civil ,PD Pithoragarh
Landmark : Plant site
Remark : Grading test for BM work

3 years ago

on Wednesday, November 9th 2022, 7:17:27 am
<span class="4">Picture Id:9068</span>
PWD Uttarakahnd
Photo (ID 9068) from Site Received
Uploader : Gopal Giri Goswami, Assistant Engineer Civil ,PD Pithoragarh
Landmark : Km 1
Remark : BM laying in km 1

3 years ago

on Friday, November 11th 2022, 8:55:24 am
<span class="4">Picture Id:9122</span>
PWD Uttarakahnd
Photo (ID 9122) from Site Received
Uploader : Gopal Giri Goswami, Assistant Engineer Civil ,PD Pithoragarh
Landmark : Km 1
Remark : BM work

3 years ago

on Tuesday, November 15th 2022, 9:27:14 am
<span class="4">Picture Id:9228</span>
PWD Uttarakahnd
Photo (ID 9228) from Site Received
Uploader : Gopal Giri Goswami, Assistant Engineer Civil ,PD Pithoragarh
Landmark : Km 2
Remark : SDBC work

3 years ago

on Thursday, January 12th 2023, 6:30:00 pm
49.72%
Financial Progress

1st Expenditure
of ₹ 4416073 (44.16 Lacs ) done.
Cummulative ₹ 44.16Lacs ( against 88.82Lacs )

3 years ago

on Tuesday, February 7th 2023, 6:30:00 pm
54.92%
Financial Progress

2nd Expenditure
of ₹ 462088 (4.62 Lacs ) done.
Cummulative ₹ 48.78Lacs ( against 88.82Lacs )

2 years ago

on Sunday, March 19th 2023, 6:30:00 pm
60.45%
Financial Progress

3rd Expenditure
of ₹ 490880 (4.91 Lacs ) done.
Cummulative ₹ 53.69Lacs ( against 88.82Lacs )

2 years ago

on Wednesday, March 29th 2023, 6:30:00 pm
99.37%
Financial Progress

4th Expenditure
of ₹ 3456677 (34.57 Lacs ) done.
Cummulative ₹ 88.26Lacs ( against 88.82Lacs )