on Thursday, February 16th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र सितारगंज के अन्तर्गत अरविन्द नगर मुख्य मार्ग से रतनफार्म नं0 09 तक मार्ग का पुनः निर्माण कार्य।
on Tuesday, February 21st 2023, 11:56:17 am
Technical Sanction
of ₹ 50.61 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1230/EE
on Sunday, May 28th 2023, 6:30:00 pm
51.22%
Financial Progress
1st Expenditure
of ₹ 2592170 (25.92 Lacs ) done.
Cummulative ₹ 25.92Lacs ( against 50.61Lacs )
on Tuesday, May 30th 2023, 6:30:00 pm
102.44%
Financial Progress
2nd Expenditure
of ₹ 2592170 (25.92 Lacs ) done.
Cummulative ₹ 51.84Lacs ( against 50.61Lacs )
on Wednesday, June 14th 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 1st time
on Friday, July 28th 2023, 6:30:00 pm
112.21%
Financial Progress
3rd Expenditure
of ₹ 494853 (4.95 Lacs ) done.
Cummulative ₹ 56.79Lacs ( against 50.61Lacs )
on Thursday, August 10th 2023, 7:59:46 am
PWD UttarakahndPhoto (ID 23487) from Site Received
Uploader : Satyapal Singh, Additional Assistant Engineer Civil ,CD Khatima
Landmark : 0.350
Remark : Proposed for Nabard 29
on Thursday, August 10th 2023, 8:01:07 am
PWD UttarakahndPhoto (ID 23488) from Site Received
Uploader : Satyapal Singh, Additional Assistant Engineer Civil ,CD Khatima
Landmark : 0.9500
Remark : Proposed for Nabard 29
on Tuesday, October 3rd 2023, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, October 12th 2023, 8:54:26 am
PWD UttarakahndPhoto (ID 24941) from Site Received
Uploader : Satyapal Singh, Additional Assistant Engineer Civil ,CD Khatima
Landmark : 2.00
Remark : राज्य योजना के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र सितारगंज के अन्तर्गत अरविन्द नगर मुख्य मार्ग से रतनफार्म नं0 09 तक मार्ग का पुनः निर्माण कार्य।
PC work with HMP Plant
on Thursday, October 19th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Tuesday, November 14th 2023, 6:30:00 pm
151.03%
Financial Progress
4th Expenditure
of ₹ 1964414 (19.64 Lacs ) done.
Cummulative ₹ 76.44Lacs ( against 50.61Lacs )
on Monday, December 18th 2023, 6:30:00 pm
99.81%
Financial Progress
5th Expenditure
of ₹ -2592170 (-25.92 Lacs ) done.
Cummulative ₹ 50.51Lacs ( against 50.61Lacs )