Refresh data
on Monday, March 20th 2023, 6:30:00 pm
Work Sanctioned
मा0 मुख्यमंत्री घोषणा संख्या 712/2021 के अन्तर्गत जनपद उधमसिंह नगर के विधानसभा क्षेत्र नानकमत्ता के अन्तर्गत ग्राम टुकड़ी में टावर से त्रिलोक सिंह के घर की ओर मार्ग का डामरीकरण का कार्य / नव निर्माण कार्य।
on Wednesday, April 12th 2023, 11:11:49 am
Technical Sanction
of ₹ 91.15 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1258/EE
on Thursday, June 15th 2023, 6:30:00 pm
10%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, August 10th 2023, 5:36:31 am
PWD UttarakahndPhoto (ID 23532) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage 0.000
Remark : Proposed for NABARD 29
on Thursday, August 10th 2023, 5:39:59 am
PWD UttarakahndPhoto (ID 23536) from Site Received
Uploader : Rizvan, Additional Assistant Engineer Civil ,CD Khatima
Landmark : Chainage 0.500
Remark : Proposed for NABARD 29
on Sunday, September 17th 2023, 6:30:00 pm
39.82%
Financial Progress
1st Expenditure
of ₹ 3629955 (36.30 Lacs ) done.
Cummulative ₹ 36.30Lacs ( against 91.15Lacs )
on Monday, September 18th 2023, 6:30:00 pm
79.65%
Financial Progress
2nd Expenditure
of ₹ 3629955 (36.30 Lacs ) done.
Cummulative ₹ 72.60Lacs ( against 91.15Lacs )
on Tuesday, October 3rd 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Wednesday, October 25th 2023, 6:30:00 pm
101.43%
Financial Progress
3rd Expenditure
of ₹ 1985012 (19.85 Lacs ) done.
Cummulative ₹ 92.45Lacs ( against 91.15Lacs )
on Tuesday, December 5th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, December 18th 2023, 6:30:00 pm
92.28%
Financial Progress
4th Expenditure
of ₹ -833472 (-8.33 Lacs ) done.
Cummulative ₹ 84.11Lacs ( against 91.15Lacs )