4 years ago

on Tuesday, June 1st 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद उधम सिंह नगर के विधानसभा क्षेत्र जसपुर के अंतर्गत रा०मा० 734 पर धरमपुर चौराहे से ग्राम मकोनिया तक मार्ग का पुनः निर्माण कार्य

4 years ago

on Friday, July 9th 2021, 11:54:11 am

Technical Sanction
of ₹ 51.95 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1181/5C

4 years ago

on Friday, August 13th 2021, 10:43:47 am
<span class="4">Picture Id:620</span>
PWD Uttarakahnd
Photo (ID 620) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 10.200 Gadhi Negi
Remark : Proposed in Nabard 27

4 years ago

on Friday, August 13th 2021, 10:57:45 am
<span class="4">Picture Id:621</span>
PWD Uttarakahnd
Photo (ID 621) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 10.200 Gadhi negi
Remark : Proposed in Nabard 27

4 years ago

on Friday, August 13th 2021, 11:09:51 am
<span class="4">Picture Id:623</span>
PWD Uttarakahnd
Photo (ID 623) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 11.800 Kashipur main road
Remark : Kashipur main Km 11 to Km 13,Proposed in Nabard 27

4 years ago

on Friday, August 13th 2021, 11:15:31 am
<span class="4">Picture Id:625</span>
PWD Uttarakahnd
Photo (ID 625) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 12.950 Durgapur
Remark : Kashipur main Km 11 to Km 13, Proposed in Nabard 27

3 years ago

on Sunday, June 19th 2022, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 1st time

3 years ago

on Wednesday, June 22nd 2022, 6:30:00 pm
27.41%
Financial Progress

1st Expenditure
of ₹ 1424000 (14.24 Lacs ) done.
Cummulative ₹ 14.24Lacs ( against 51.95Lacs )

3 years ago

on Sunday, October 23rd 2022, 6:30:00 pm
42.95%
Financial Progress

2nd Expenditure
of ₹ 807114 (8.07 Lacs ) done.
Cummulative ₹ 22.31Lacs ( against 51.95Lacs )

3 years ago

on Tuesday, November 15th 2022, 6:30:00 pm
60%

Physical Progress
Physical Progress Reported at 2nd time

3 years ago

on Thursday, November 24th 2022, 6:30:00 pm
65.97%
Financial Progress

3rd Expenditure
of ₹ 1196160 (11.96 Lacs ) done.
Cummulative ₹ 34.27Lacs ( against 51.95Lacs )

3 years ago

on Wednesday, December 7th 2022, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Sunday, March 19th 2023, 6:30:00 pm
100.00%
Financial Progress

4th Expenditure
of ₹ 1767790 (17.68 Lacs ) done.
Cummulative ₹ 51.95Lacs ( against 51.95Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable