on Tuesday, June 1st 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद उधम सिंह नगर के विधानसभा क्षेत्र जसपुर के अंतर्गत रा०मा० 734 पर धरमपुर चौराहे से ग्राम मकोनिया तक मार्ग का पुनः निर्माण कार्य
on Friday, July 9th 2021, 11:54:11 am
Technical Sanction
of ₹ 51.95 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 1181/5C
on Friday, August 13th 2021, 10:43:47 am
PWD UttarakahndPhoto (ID 620) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 10.200 Gadhi Negi
Remark : Proposed in Nabard 27
on Friday, August 13th 2021, 10:57:45 am
PWD UttarakahndPhoto (ID 621) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 10.200 Gadhi negi
Remark : Proposed in Nabard 27
on Friday, August 13th 2021, 11:09:51 am
PWD UttarakahndPhoto (ID 623) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 11.800 Kashipur main road
Remark : Kashipur main Km 11 to Km 13,Proposed in Nabard 27
on Friday, August 13th 2021, 11:15:31 am
PWD UttarakahndPhoto (ID 625) from Site Received
Uploader : Nafeesh Ahamad, Assistant Engineer Civil ,NH Div Dhumakot
Landmark : 12.950 Durgapur
Remark : Kashipur main Km 11 to Km 13, Proposed in Nabard 27
on Sunday, June 19th 2022, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 1st time
on Wednesday, June 22nd 2022, 6:30:00 pm
27.41%
Financial Progress
1st Expenditure
of ₹ 1424000 (14.24 Lacs ) done.
Cummulative ₹ 14.24Lacs ( against 51.95Lacs )
on Sunday, October 23rd 2022, 6:30:00 pm
42.95%
Financial Progress
2nd Expenditure
of ₹ 807114 (8.07 Lacs ) done.
Cummulative ₹ 22.31Lacs ( against 51.95Lacs )
on Tuesday, November 15th 2022, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, November 24th 2022, 6:30:00 pm
65.97%
Financial Progress
3rd Expenditure
of ₹ 1196160 (11.96 Lacs ) done.
Cummulative ₹ 34.27Lacs ( against 51.95Lacs )
on Wednesday, December 7th 2022, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Sunday, March 19th 2023, 6:30:00 pm
100.00%
Financial Progress
4th Expenditure
of ₹ 1767790 (17.68 Lacs ) done.
Cummulative ₹ 51.95Lacs ( against 51.95Lacs )