Refresh data
on Monday, September 13th 2021, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद उधमसिंहनगर के विधान सभा क्षेत्र बाजपुर में गिरधई से महुवाखेडागंज मोटर मार्ग का के0एस0 इंडस्ट्रीज से महुवाखेडा तक पुनः निर्माण कार्य।
on Monday, June 20th 2022, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Thursday, June 23rd 2022, 6:30:00 pm
0.09%
Financial Progress
1st Expenditure
of ₹ 10000 (0.10 Lacs ) done.
Cummulative ₹ 0.10Lacs ( against 108.99Lacs )
on Wednesday, July 6th 2022, 6:30:00 pm
6.51%
Financial Progress
2nd Expenditure
of ₹ 700000 (7.00 Lacs ) done.
Cummulative ₹ 7.10Lacs ( against 108.99Lacs )
on Thursday, August 25th 2022, 12:21:13 am
PWD UttarakahndPhoto (ID 7384) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Thursday, August 25th 2022, 12:24:20 am
PWD UttarakahndPhoto (ID 7385) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, August 27th 2022, 6:30:00 pm
10.15%
Financial Progress
3rd Expenditure
of ₹ 396473 (3.96 Lacs ) done.
Cummulative ₹ 11.06Lacs ( against 108.99Lacs )
on Monday, August 29th 2022, 11:58:04 pm
PWD UttarakahndPhoto (ID 7564) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 1.500
Remark : WMM work in progress
on Tuesday, August 30th 2022, 12:01:16 am
PWD UttarakahndPhoto (ID 7565) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Tuesday, August 30th 2022, 12:14:51 am
PWD UttarakahndPhoto (ID 7567) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, August 31st 2022, 11:44:22 pm
PWD UttarakahndPhoto (ID 7638) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, August 31st 2022, 11:53:28 pm
PWD UttarakahndPhoto (ID 7639) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, September 3rd 2022, 12:28:40 am
PWD UttarakahndPhoto (ID 7688) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 1.800
Remark : Construction of drain in progress
on Saturday, September 3rd 2022, 12:31:04 am
PWD UttarakahndPhoto (ID 7689) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, September 3rd 2022, 12:42:58 am
PWD UttarakahndPhoto (ID 7691) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Sunday, September 4th 2022, 11:00:30 pm
PWD UttarakahndPhoto (ID 7730) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Monday, September 12th 2022, 11:58:51 pm
PWD UttarakahndPhoto (ID 7901) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.200
Remark : WMM Surface after compaction
on Tuesday, September 13th 2022, 12:02:42 am
PWD UttarakahndPhoto (ID 7903) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Tuesday, September 13th 2022, 12:25:34 am
PWD UttarakahndPhoto (ID 7906) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, September 21st 2022, 12:23:15 am
PWD UttarakahndPhoto (ID 8064) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, September 21st 2022, 1:02:03 am
PWD UttarakahndPhoto (ID 8072) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, September 21st 2022, 1:03:40 am
PWD UttarakahndPhoto (ID 8073) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Friday, September 30th 2022, 1:23:56 am
PWD UttarakahndPhoto (ID 8261) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Friday, September 30th 2022, 1:25:54 am
PWD UttarakahndPhoto (ID 8262) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Sunday, October 23rd 2022, 6:30:00 pm
33.16%
Financial Progress
4th Expenditure
of ₹ 2507483 (25.07 Lacs ) done.
Cummulative ₹ 36.14Lacs ( against 108.99Lacs )
on Thursday, November 10th 2022, 12:30:50 am
PWD UttarakahndPhoto (ID 9086) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 2250
Remark : PC work in progress
on Thursday, November 10th 2022, 12:33:16 am
PWD UttarakahndPhoto (ID 9087) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Km.214 of SH-32
Remark : BC WORK IN PROGRESS
on Thursday, November 10th 2022, 12:42:34 am
PWD UttarakahndPhoto (ID 9088) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Thursday, November 10th 2022, 4:31:43 am
PWD UttarakahndPhoto (ID 9096) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Thursday, November 10th 2022, 5:15:09 am
PWD UttarakahndPhoto (ID 9101) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Friday, November 11th 2022, 12:00:26 am
PWD UttarakahndPhoto (ID 9132) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Km1 X/s no4
Remark : Checking of gradation
on Friday, November 11th 2022, 11:38:48 pm
PWD UttarakahndPhoto (ID 9134) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, November 12th 2022, 12:12:16 am
PWD UttarakahndPhoto (ID 9137) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Km.216 of SH-32
Remark : BC WORK IN PROGRESS
on Saturday, November 12th 2022, 5:43:48 am
PWD UttarakahndPhoto (ID 9146) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Km.216 of SH-32
Remark : BC WORK IN PROGRESS
on Saturday, November 12th 2022, 8:57:10 am
PWD UttarakahndPhoto (ID 9148) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : Ch 6.300
Remark : Laying of B.M.
on Sunday, November 20th 2022, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, November 24th 2022, 6:30:00 pm
46.93%
Financial Progress
5th Expenditure
of ₹ 1500800 (15.01 Lacs ) done.
Cummulative ₹ 51.15Lacs ( against 108.99Lacs )
on Saturday, November 26th 2022, 12:30:06 am
PWD UttarakahndPhoto (ID 12012) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, November 26th 2022, 12:56:35 am
PWD UttarakahndPhoto (ID 12018) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, December 7th 2022, 6:30:00 pm
85%
Physical Progress
Physical Progress Reported at 3rd time
on Friday, December 9th 2022, 12:42:20 am
PWD UttarakahndPhoto (ID 13710) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Monday, December 19th 2022, 12:54:53 am
PWD UttarakahndPhoto (ID 14434) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Wednesday, March 22nd 2023, 6:30:00 pm
73.50%
Financial Progress
6th Expenditure
of ₹ 2895551 (28.96 Lacs ) done.
Cummulative ₹ 80.10Lacs ( against 108.99Lacs )
on Thursday, April 6th 2023, 7:28:13 am
PWD UttarakahndPhoto (ID 19107) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Thursday, April 6th 2023, 7:42:04 am
PWD UttarakahndPhoto (ID 19108) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress
on Saturday, April 8th 2023, 7:14:45 am
PWD UttarakahndPhoto (ID 19120) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.050
Remark : Rolling work in progress