Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उधमसिंहनगर के विधानसभा क्षेत्र बाजपुर में मुकुन्दपुर पैगा ढकिया गुलाबो मार्ग (राज्य मार्ग सं0 105) के चैनेज 13.700 से चैनेज 16.000 किमी0 तक (वीरपुर से कटैया) पुनःनिर्माण/ सुदृढ़ीकरण का कार्य।
on Friday, September 9th 2022, 11:03:30 am
Technical Sanction
of ₹ 452.68 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4514/01Yata(Ksp)-Hld/022
on Sunday, October 23rd 2022, 6:30:00 pm
0.04%
Financial Progress
1st Expenditure
of ₹ 17622 (0.18 Lacs ) done.
Cummulative ₹ 0.18Lacs ( against 452.68Lacs )
on Wednesday, December 7th 2022, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, March 19th 2023, 6:30:00 pm
48.37%
Financial Progress
2nd Expenditure
of ₹ 21877153 (218.77 Lacs ) done.
Cummulative ₹ 218.95Lacs ( against 452.68Lacs )
on Saturday, April 8th 2023, 6:30:00 pm
50%
Physical Progress
Physical Progress Reported at 2nd time
on Monday, May 22nd 2023, 6:30:00 pm
65.09%
Financial Progress
3rd Expenditure
of ₹ 7571775 (75.72 Lacs ) done.
Cummulative ₹ 294.67Lacs ( against 452.68Lacs )
on Wednesday, May 31st 2023, 7:28:12 am
PWD UttarakahndPhoto (ID 20165) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.800
Remark : DBM 3rd layer laying in progress
on Thursday, June 1st 2023, 5:15:43 am
PWD UttarakahndPhoto (ID 20180) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 14.850
Remark : DBM 3rd layer laying in progress
on Wednesday, June 7th 2023, 6:30:00 pm
65.21%
Financial Progress
5th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 295.21Lacs ( against 452.68Lacs )
on Wednesday, June 7th 2023, 6:30:00 pm
79.11%
Financial Progress
6th Expenditure
of ₹ 6288836 (62.89 Lacs ) done.
Cummulative ₹ 358.09Lacs ( against 452.68Lacs )
on Wednesday, June 7th 2023, 6:30:00 pm
65.15%
Financial Progress
4th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 294.94Lacs ( against 452.68Lacs )
on Friday, June 9th 2023, 4:43:19 am
PWD UttarakahndPhoto (ID 20633) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.400
Remark : B C laying in progress
on Friday, June 9th 2023, 10:11:28 am
PWD UttarakahndPhoto (ID 20665) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.700
Remark : B C laying in progress
on Tuesday, June 13th 2023, 6:30:00 pm
91.99%
Financial Progress
7th Expenditure
of ₹ 5833209 (58.33 Lacs ) done.
Cummulative ₹ 416.43Lacs ( against 452.68Lacs )
on Wednesday, June 14th 2023, 6:30:00 pm
92.09%
Financial Progress
8th Expenditure
of ₹ 43325 (0.43 Lacs ) done.
Cummulative ₹ 416.86Lacs ( against 452.68Lacs )
on Wednesday, June 14th 2023, 6:30:00 pm
92.20%
Financial Progress
9th Expenditure
of ₹ 48921 (0.49 Lacs ) done.
Cummulative ₹ 417.35Lacs ( against 452.68Lacs )
on Thursday, June 29th 2023, 6:30:00 pm
92.20%
Financial Progress
10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 417.35Lacs ( against 452.68Lacs )
on Thursday, July 13th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, August 21st 2023, 6:30:00 pm
92.61%
Financial Progress
11th Expenditure
of ₹ 186971 (1.87 Lacs ) done.
Cummulative ₹ 419.22Lacs ( against 452.68Lacs )
on Thursday, August 24th 2023, 6:30:00 pm
92.61%
Financial Progress
12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 419.22Lacs ( against 452.68Lacs )
on Monday, August 28th 2023, 6:30:00 pm
98.34%
Financial Progress
13th Expenditure
of ₹ 2592480 (25.92 Lacs ) done.
Cummulative ₹ 445.14Lacs ( against 452.68Lacs )
on Monday, November 6th 2023, 6:30:00 pm
98.50%
Financial Progress
14th Expenditure
of ₹ 73042 (0.73 Lacs ) done.
Cummulative ₹ 445.87Lacs ( against 452.68Lacs )
on Monday, January 15th 2024, 6:30:00 pm
99.34%
Financial Progress
15th Expenditure
of ₹ 382741 (3.83 Lacs ) done.
Cummulative ₹ 449.70Lacs ( against 452.68Lacs )
on Tuesday, January 16th 2024, 6:30:00 pm
99.38%
Financial Progress
16th Expenditure
of ₹ 19363 (0.19 Lacs ) done.
Cummulative ₹ 449.89Lacs ( against 452.68Lacs )
on Tuesday, February 20th 2024, 6:30:00 pm
99.56%
Financial Progress
17th Expenditure
of ₹ 78066 (0.78 Lacs ) done.
Cummulative ₹ 450.68Lacs ( against 452.68Lacs )