3 years ago

on Wednesday, August 3rd 2022, 6:30:00 pm
Work Sanctioned
राज्य योजना के अन्तर्गत जनपद उधमसिंहनगर के विधानसभा क्षेत्र बाजपुर में मुकुन्दपुर पैगा ढकिया गुलाबो मार्ग (राज्य मार्ग सं0 105) के चैनेज 13.700 से चैनेज 16.000 किमी0 तक (वीरपुर से कटैया) पुनःनिर्माण/ सुदृढ़ीकरण का कार्य।

3 years ago

on Friday, September 9th 2022, 11:03:30 am

Technical Sanction
of ₹ 452.68 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 4514/01Yata(Ksp)-Hld/022

3 years ago

on Sunday, October 23rd 2022, 6:30:00 pm
0.04%
Financial Progress

1st Expenditure
of ₹ 17622 (0.18 Lacs ) done.
Cummulative ₹ 0.18Lacs ( against 452.68Lacs )

3 years ago

on Wednesday, December 7th 2022, 6:30:00 pm
5%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Sunday, March 19th 2023, 6:30:00 pm
48.37%
Financial Progress

2nd Expenditure
of ₹ 21877153 (218.77 Lacs ) done.
Cummulative ₹ 218.95Lacs ( against 452.68Lacs )

2 years ago

on Saturday, April 8th 2023, 6:30:00 pm
50%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Monday, May 22nd 2023, 6:30:00 pm
65.09%
Financial Progress

3rd Expenditure
of ₹ 7571775 (75.72 Lacs ) done.
Cummulative ₹ 294.67Lacs ( against 452.68Lacs )

2 years ago

on Wednesday, May 31st 2023, 7:28:12 am
<span class="4">Picture Id:20165</span>
PWD Uttarakahnd
Photo (ID 20165) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.800
Remark : DBM 3rd layer laying in progress

2 years ago

on Thursday, June 1st 2023, 5:15:43 am
<span class="4">Picture Id:20180</span>
PWD Uttarakahnd
Photo (ID 20180) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 14.850
Remark : DBM 3rd layer laying in progress

2 years ago

on Wednesday, June 7th 2023, 6:30:00 pm
65.21%
Financial Progress

5th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 295.21Lacs ( against 452.68Lacs )

2 years ago

on Wednesday, June 7th 2023, 6:30:00 pm
79.11%
Financial Progress

6th Expenditure
of ₹ 6288836 (62.89 Lacs ) done.
Cummulative ₹ 358.09Lacs ( against 452.68Lacs )

2 years ago

on Wednesday, June 7th 2023, 6:30:00 pm
65.15%
Financial Progress

4th Expenditure
of ₹ 27000 (0.27 Lacs ) done.
Cummulative ₹ 294.94Lacs ( against 452.68Lacs )

2 years ago

on Friday, June 9th 2023, 4:43:19 am
<span class="4">Picture Id:20633</span>
PWD Uttarakahnd
Photo (ID 20633) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.400
Remark : B C laying in progress

2 years ago

on Friday, June 9th 2023, 10:11:28 am
<span class="4">Picture Id:20665</span>
PWD Uttarakahnd
Photo (ID 20665) from Site Received
Uploader : Chetan Bhatt, Additional Assistant Engineer Civil ,PD Lansdown
Landmark : 15.700
Remark : B C laying in progress

2 years ago

on Tuesday, June 13th 2023, 6:30:00 pm
91.99%
Financial Progress

7th Expenditure
of ₹ 5833209 (58.33 Lacs ) done.
Cummulative ₹ 416.43Lacs ( against 452.68Lacs )

2 years ago

on Wednesday, June 14th 2023, 6:30:00 pm
92.09%
Financial Progress

8th Expenditure
of ₹ 43325 (0.43 Lacs ) done.
Cummulative ₹ 416.86Lacs ( against 452.68Lacs )

2 years ago

on Wednesday, June 14th 2023, 6:30:00 pm
92.20%
Financial Progress

9th Expenditure
of ₹ 48921 (0.49 Lacs ) done.
Cummulative ₹ 417.35Lacs ( against 452.68Lacs )

2 years ago

on Thursday, June 29th 2023, 6:30:00 pm
92.20%
Financial Progress

10th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 417.35Lacs ( against 452.68Lacs )

2 years ago

on Thursday, July 13th 2023, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Monday, August 21st 2023, 6:30:00 pm
92.61%
Financial Progress

11th Expenditure
of ₹ 186971 (1.87 Lacs ) done.
Cummulative ₹ 419.22Lacs ( against 452.68Lacs )

2 years ago

on Thursday, August 24th 2023, 6:30:00 pm
92.61%
Financial Progress

12th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 419.22Lacs ( against 452.68Lacs )

2 years ago

on Monday, August 28th 2023, 6:30:00 pm
98.34%
Financial Progress

13th Expenditure
of ₹ 2592480 (25.92 Lacs ) done.
Cummulative ₹ 445.14Lacs ( against 452.68Lacs )

2 years ago

on Monday, November 6th 2023, 6:30:00 pm
98.50%
Financial Progress

14th Expenditure
of ₹ 73042 (0.73 Lacs ) done.
Cummulative ₹ 445.87Lacs ( against 452.68Lacs )

2 years ago

on Monday, January 15th 2024, 6:30:00 pm
99.34%
Financial Progress

15th Expenditure
of ₹ 382741 (3.83 Lacs ) done.
Cummulative ₹ 449.70Lacs ( against 452.68Lacs )

2 years ago

on Tuesday, January 16th 2024, 6:30:00 pm
99.38%
Financial Progress

16th Expenditure
of ₹ 19363 (0.19 Lacs ) done.
Cummulative ₹ 449.89Lacs ( against 452.68Lacs )

2 years ago

on Tuesday, February 20th 2024, 6:30:00 pm
99.56%
Financial Progress

17th Expenditure
of ₹ 78066 (0.78 Lacs ) done.
Cummulative ₹ 450.68Lacs ( against 452.68Lacs )