2 years ago

on Monday, March 27th 2023, 6:30:00 pm
Work Sanctioned
राज्य योजना के अंतर्गत जनपद ऊधमसिंहनगर के विधानसभा क्षेत्र गदरपुर के अंतर्गत बांसखेडा गडी से बसन सिंह आदि के घर तक मार्ग का पुनः निर्माण कार्य।

2 years ago

on Wednesday, March 29th 2023, 11:14:25 am

Technical Sanction
of ₹ 84.75 Lacs

1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 680/TS

2 years ago

on Thursday, July 13th 2023, 6:30:00 pm
15%

Physical Progress
Physical Progress Reported at 1st time

2 years ago

on Tuesday, July 25th 2023, 6:30:00 pm
0.00%
Financial Progress

1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 84.75Lacs )

2 years ago

on Thursday, July 27th 2023, 6:30:00 pm
4.17%
Financial Progress

2nd Expenditure
of ₹ 353582 (3.54 Lacs ) done.
Cummulative ₹ 3.54Lacs ( against 84.75Lacs )

2 years ago

on Sunday, August 6th 2023, 6:30:00 pm
20%

Physical Progress
Physical Progress Reported at 2nd time

2 years ago

on Tuesday, September 5th 2023, 6:30:00 pm
5.10%
Financial Progress

3rd Expenditure
of ₹ 78247 (0.78 Lacs ) done.
Cummulative ₹ 4.32Lacs ( against 84.75Lacs )

2 years ago

on Sunday, September 24th 2023, 6:30:00 pm
5.49%
Financial Progress

4th Expenditure
of ₹ 33393 (0.33 Lacs ) done.
Cummulative ₹ 4.65Lacs ( against 84.75Lacs )

2 years ago

on Tuesday, September 26th 2023, 6:30:00 pm
10.09%
Financial Progress

5th Expenditure
of ₹ 390219 (3.90 Lacs ) done.
Cummulative ₹ 8.55Lacs ( against 84.75Lacs )

2 years ago

on Sunday, October 8th 2023, 6:30:00 pm
25%

Physical Progress
Physical Progress Reported at 3rd time

2 years ago

on Thursday, October 12th 2023, 6:30:00 pm
10.17%
Financial Progress

6th Expenditure
of ₹ 6271 (0.06 Lacs ) done.
Cummulative ₹ 8.62Lacs ( against 84.75Lacs )

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
10.38%
Financial Progress

7th Expenditure
of ₹ 18290 (0.18 Lacs ) done.
Cummulative ₹ 8.80Lacs ( against 84.75Lacs )

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
30%

Physical Progress
Physical Progress Reported at 4th time

2 years ago

on Thursday, November 9th 2023, 6:30:00 pm
11.40%
Financial Progress

8th Expenditure
of ₹ 85810 (0.86 Lacs ) done.
Cummulative ₹ 9.66Lacs ( against 84.75Lacs )

2 years ago

on Friday, November 24th 2023, 6:30:00 pm
11.40%
Financial Progress

9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 9.66Lacs ( against 84.75Lacs )

2 years ago

on Saturday, February 3rd 2024, 6:15:05 am
<span class="4">Picture Id:35544</span>
PWD Uttarakahnd
Photo (ID 35544) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.250
Remark : WBM G-3 WORK IN PROGRESS

2 years ago

on Wednesday, February 7th 2024, 6:30:00 pm
11.86%
Financial Progress

10th Expenditure
of ₹ 39700 (0.40 Lacs ) done.
Cummulative ₹ 10.06Lacs ( against 84.75Lacs )

2 years ago

on Tuesday, February 20th 2024, 6:30:00 pm
20.55%
Financial Progress

11th Expenditure
of ₹ 736358 (7.36 Lacs ) done.
Cummulative ₹ 17.42Lacs ( against 84.75Lacs )

a year ago

on Tuesday, March 5th 2024, 6:30:00 pm
35%

Physical Progress
Physical Progress Reported at 5th time

a year ago

on Wednesday, April 10th 2024, 6:30:00 pm
55%

Physical Progress
Physical Progress Reported at 6th time

a year ago

on Tuesday, May 21st 2024, 6:30:00 pm
20.92%
Financial Progress

12th Expenditure
of ₹ 30885 (0.31 Lacs ) done.
Cummulative ₹ 17.73Lacs ( against 84.75Lacs )

a year ago

on Friday, June 14th 2024, 6:30:00 pm
21.68%
Financial Progress

13th Expenditure
of ₹ 64966 (0.65 Lacs ) done.
Cummulative ₹ 18.38Lacs ( against 84.75Lacs )

a year ago

on Wednesday, June 26th 2024, 10:46:25 am
<span class="4">Picture Id:47219</span>
PWD Uttarakahnd
Photo (ID 47219) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.400
Remark : PC

a year ago

on Wednesday, June 26th 2024, 10:54:26 am
<span class="4">Picture Id:47220</span>
PWD Uttarakahnd
Photo (ID 47220) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : .900
Remark : Pc

a year ago

on Wednesday, June 26th 2024, 6:30:00 pm
75%

Physical Progress
Physical Progress Reported at 7th time

a year ago

on Wednesday, August 21st 2024, 6:30:00 pm
31.40%
Financial Progress

14th Expenditure
of ₹ 823197 (8.23 Lacs ) done.
Cummulative ₹ 26.61Lacs ( against 84.75Lacs )

9 months ago

on Wednesday, December 4th 2024, 6:30:00 pm
40.26%
Financial Progress

15th Expenditure
of ₹ 751529 (7.52 Lacs ) done.
Cummulative ₹ 34.12Lacs ( against 84.75Lacs )

8 months ago

on Thursday, December 19th 2024, 6:30:00 pm
41.38%
Financial Progress

16th Expenditure
of ₹ 94400 (0.94 Lacs ) done.
Cummulative ₹ 35.07Lacs ( against 84.75Lacs )

8 months ago

on Friday, December 20th 2024, 6:30:00 pm
100%

Physical Progress
Physical Progress Reported at 8th time

8 months ago

on Thursday, December 26th 2024, 6:30:00 pm
63.06%
Financial Progress

17th Expenditure
of ₹ 1837454 (18.37 Lacs ) done.
Cummulative ₹ 53.44Lacs ( against 84.75Lacs )

AI layer

AI Road
AI Bridge
10000 km
5000 mi
Unavailable
refresh data by PWD Uttarakhand Engineeres | View code by HandsOnDataViz with Leaflet | © OpenStreetMap contributors