Work Sanctioned
राज्य योजना के अंतर्गत जनपद ऊधमसिंहनगर के विधानसभा क्षेत्र गदरपुर के अंतर्गत बांसखेडा गडी से बसन सिंह आदि के घर तक मार्ग का पुनः निर्माण कार्य।
on Wednesday, March 29th 2023, 11:14:25 am
Technical Sanction
of ₹ 84.75 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 680/TS
on Thursday, July 13th 2023, 6:30:00 pm
15%
Physical Progress
Physical Progress Reported at 1st time
on Tuesday, July 25th 2023, 6:30:00 pm
0.00%
Financial Progress
1st Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 0.00Lacs ( against 84.75Lacs )
on Thursday, July 27th 2023, 6:30:00 pm
4.17%
Financial Progress
2nd Expenditure
of ₹ 353582 (3.54 Lacs ) done.
Cummulative ₹ 3.54Lacs ( against 84.75Lacs )
on Sunday, August 6th 2023, 6:30:00 pm
20%
Physical Progress
Physical Progress Reported at 2nd time
on Tuesday, September 5th 2023, 6:30:00 pm
5.10%
Financial Progress
3rd Expenditure
of ₹ 78247 (0.78 Lacs ) done.
Cummulative ₹ 4.32Lacs ( against 84.75Lacs )
on Sunday, September 24th 2023, 6:30:00 pm
5.49%
Financial Progress
4th Expenditure
of ₹ 33393 (0.33 Lacs ) done.
Cummulative ₹ 4.65Lacs ( against 84.75Lacs )
on Tuesday, September 26th 2023, 6:30:00 pm
10.09%
Financial Progress
5th Expenditure
of ₹ 390219 (3.90 Lacs ) done.
Cummulative ₹ 8.55Lacs ( against 84.75Lacs )
on Sunday, October 8th 2023, 6:30:00 pm
25%
Physical Progress
Physical Progress Reported at 3rd time
on Thursday, October 12th 2023, 6:30:00 pm
10.17%
Financial Progress
6th Expenditure
of ₹ 6271 (0.06 Lacs ) done.
Cummulative ₹ 8.62Lacs ( against 84.75Lacs )
on Thursday, November 9th 2023, 6:30:00 pm
10.38%
Financial Progress
7th Expenditure
of ₹ 18290 (0.18 Lacs ) done.
Cummulative ₹ 8.80Lacs ( against 84.75Lacs )
on Thursday, November 9th 2023, 6:30:00 pm
30%
Physical Progress
Physical Progress Reported at 4th time
on Thursday, November 9th 2023, 6:30:00 pm
11.40%
Financial Progress
8th Expenditure
of ₹ 85810 (0.86 Lacs ) done.
Cummulative ₹ 9.66Lacs ( against 84.75Lacs )
on Friday, November 24th 2023, 6:30:00 pm
11.40%
Financial Progress
9th Expenditure
of ₹ 0 (0.00 Lacs ) done.
Cummulative ₹ 9.66Lacs ( against 84.75Lacs )
on Saturday, February 3rd 2024, 6:15:05 am
PWD UttarakahndPhoto (ID 35544) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.250
Remark : WBM G-3 WORK IN PROGRESS
on Wednesday, February 7th 2024, 6:30:00 pm
11.86%
Financial Progress
10th Expenditure
of ₹ 39700 (0.40 Lacs ) done.
Cummulative ₹ 10.06Lacs ( against 84.75Lacs )
on Tuesday, February 20th 2024, 6:30:00 pm
20.55%
Financial Progress
11th Expenditure
of ₹ 736358 (7.36 Lacs ) done.
Cummulative ₹ 17.42Lacs ( against 84.75Lacs )
on Tuesday, March 5th 2024, 6:30:00 pm
35%
Physical Progress
Physical Progress Reported at 5th time
on Wednesday, April 10th 2024, 6:30:00 pm
55%
Physical Progress
Physical Progress Reported at 6th time
on Tuesday, May 21st 2024, 6:30:00 pm
20.92%
Financial Progress
12th Expenditure
of ₹ 30885 (0.31 Lacs ) done.
Cummulative ₹ 17.73Lacs ( against 84.75Lacs )
on Friday, June 14th 2024, 6:30:00 pm
21.68%
Financial Progress
13th Expenditure
of ₹ 64966 (0.65 Lacs ) done.
Cummulative ₹ 18.38Lacs ( against 84.75Lacs )
on Wednesday, June 26th 2024, 10:46:25 am
PWD UttarakahndPhoto (ID 47219) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : 1.400
Remark : PC
on Wednesday, June 26th 2024, 10:54:26 am
PWD UttarakahndPhoto (ID 47220) from Site Received
Uploader : Rajesh Paintola, Additional Assistant Engineer Civil ,CD Kashipur
Landmark : .900
Remark : Pc
on Wednesday, June 26th 2024, 6:30:00 pm
75%
Physical Progress
Physical Progress Reported at 7th time
on Wednesday, August 21st 2024, 6:30:00 pm
31.40%
Financial Progress
14th Expenditure
of ₹ 823197 (8.23 Lacs ) done.
Cummulative ₹ 26.61Lacs ( against 84.75Lacs )
on Wednesday, December 4th 2024, 6:30:00 pm
40.26%
Financial Progress
15th Expenditure
of ₹ 751529 (7.52 Lacs ) done.
Cummulative ₹ 34.12Lacs ( against 84.75Lacs )
on Thursday, December 19th 2024, 6:30:00 pm
41.38%
Financial Progress
16th Expenditure
of ₹ 94400 (0.94 Lacs ) done.
Cummulative ₹ 35.07Lacs ( against 84.75Lacs )
on Friday, December 20th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 8th time
on Thursday, December 26th 2024, 6:30:00 pm
63.06%
Financial Progress
17th Expenditure
of ₹ 1837454 (18.37 Lacs ) done.
Cummulative ₹ 53.44Lacs ( against 84.75Lacs )