on Monday, April 23rd 2018, 6:30:00 pm
Work Sanctioned
माननीय मुख्यमंत्री घोषणा संख्या- 184/2017 के अन्तर्गत जनपद उत्तरकाशी के विधानसभा क्षेत्र गंगोत्री के अन्तर्गत पट्टी धनारी मे पिपली (थाती बैण्ड) से धारकोट-मुसड़गांव तक मोटर मार्ग का पुनर्निर्माण एवं डामरीकरण (24मी0 स्पान सिंगल लेन स्टील गर्डर सेतु सहित) का कार्य
on Friday, January 31st 2020, 6:30:00 pm
0.93%
Financial Progress
1st Expenditure
of ₹ 295766 (2.96 Lacs ) done.
Cummulative ₹ 2.96Lacs ( against 318.86Lacs )
on Saturday, February 29th 2020, 6:30:00 pm
13.15%
Financial Progress
2nd Expenditure
of ₹ 3896881 (38.97 Lacs ) done.
Cummulative ₹ 41.93Lacs ( against 318.86Lacs )
on Thursday, April 30th 2020, 6:30:00 pm
9.11%
Financial Progress
3rd Expenditure
of ₹ -1287154 (-12.87 Lacs ) done.
Cummulative ₹ 29.05Lacs ( against 318.86Lacs )
on Thursday, May 7th 2020, 6:30:00 pm
Technical Sanction
of ₹ 354.29 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. CE. No. 872/06yata-Pauri (Pra. Kh. Uk) 20-21
on Friday, July 31st 2020, 6:30:00 pm
10.03%
Financial Progress
4th Expenditure
of ₹ 291460 (2.91 Lacs ) done.
Cummulative ₹ 31.97Lacs ( against 318.86Lacs )
on Monday, November 30th 2020, 6:30:00 pm
22.86%
Financial Progress
5th Expenditure
of ₹ 4093300 (40.93 Lacs ) done.
Cummulative ₹ 72.90Lacs ( against 318.86Lacs )
on Sunday, January 31st 2021, 6:30:00 pm
29.85%
Financial Progress
6th Expenditure
of ₹ 2228008 (22.28 Lacs ) done.
Cummulative ₹ 95.18Lacs ( against 318.86Lacs )
on Sunday, February 28th 2021, 6:30:00 pm
41.81%
Financial Progress
7th Expenditure
of ₹ 3812902 (38.13 Lacs ) done.
Cummulative ₹ 133.31Lacs ( against 318.86Lacs )
on Friday, July 9th 2021, 6:30:00 pm
80%
Physical Progress
Physical Progress Reported at 1st time
on Saturday, July 31st 2021, 6:30:00 pm
60.48%
Financial Progress
8th Expenditure
of ₹ 5954679 (59.55 Lacs ) done.
Cummulative ₹ 192.86Lacs ( against 318.86Lacs )
on Saturday, August 21st 2021, 2:52:53 am
PWD UttarakahndPhoto (ID 1040) from Site Received
Uploader : Virender Singh Chauhan, Assistant Engineer Civil ,PD Uttarkashi
Landmark : 2.800
Remark : Laying WBM G-III
on Saturday, August 21st 2021, 3:11:52 am
PWD UttarakahndPhoto (ID 1041) from Site Received
Uploader : Virender Singh Chauhan, Assistant Engineer Civil ,PD Uttarkashi
Landmark : 2.900
Remark : WBM G-III
on Thursday, August 26th 2021, 11:53:21 pm
PWD UttarakahndPhoto (ID 1104) from Site Received
Uploader : Virender Singh Chauhan, Assistant Engineer Civil ,PD Uttarkashi
Landmark : 1.025
Remark : Abutment
on Thursday, August 26th 2021, 11:56:03 pm
PWD UttarakahndPhoto (ID 1105) from Site Received
Uploader : Virender Singh Chauhan, Assistant Engineer Civil ,PD Uttarkashi
Landmark : 1.020
Remark : Right abutment
on Thursday, September 30th 2021, 6:30:00 pm
65.49%
Financial Progress
9th Expenditure
of ₹ 1595511 (15.96 Lacs ) done.
Cummulative ₹ 208.81Lacs ( against 318.86Lacs )
on Tuesday, November 30th 2021, 6:30:00 pm
66.41%
Financial Progress
10th Expenditure
of ₹ 295457 (2.95 Lacs ) done.
Cummulative ₹ 211.77Lacs ( against 318.86Lacs )
on Monday, January 31st 2022, 6:30:00 pm
71.91%
Financial Progress
11th Expenditure
of ₹ 1753585 (17.54 Lacs ) done.
Cummulative ₹ 229.30Lacs ( against 318.86Lacs )
on Wednesday, March 30th 2022, 6:30:00 pm
90.45%
Financial Progress
12th Expenditure
of ₹ 5911000 (59.11 Lacs ) done.
Cummulative ₹ 288.41Lacs ( against 318.86Lacs )
on Sunday, January 29th 2023, 6:30:00 pm
90.70%
Financial Progress
13th Expenditure
of ₹ 78588 (0.79 Lacs ) done.
Cummulative ₹ 289.20Lacs ( against 318.86Lacs )
on Monday, February 27th 2023, 6:30:00 pm
93.77%
Financial Progress
14th Expenditure
of ₹ 980043 (9.80 Lacs ) done.
Cummulative ₹ 299.00Lacs ( against 318.86Lacs )
on Thursday, March 30th 2023, 6:30:00 pm
99.38%
Financial Progress
15th Expenditure
of ₹ 1787056 (17.87 Lacs ) done.
Cummulative ₹ 316.87Lacs ( against 318.86Lacs )