Refresh data
on Friday, December 23rd 2022, 6:30:00 pm
Work Sanctioned
जिलाधिकारी कार्यालय परिसर मे स्मार्ट कंट्रोल रूम का स्थापन कार्य।
on Monday, December 26th 2022, 8:35:38 am
Technical Sanction
of ₹ 40.05 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. EE. No. 28/1C
on Monday, February 6th 2023, 6:30:00 pm
5%
Physical Progress
Physical Progress Reported at 1st time
on Monday, February 27th 2023, 6:30:00 pm
16.65%
Financial Progress
1st Expenditure
of ₹ 667000 (6.67 Lacs ) done.
Cummulative ₹ 6.67Lacs ( against 40.05Lacs )
on Thursday, March 2nd 2023, 6:30:00 pm
60%
Physical Progress
Physical Progress Reported at 2nd time
on Thursday, March 30th 2023, 6:30:00 pm
45.61%
Financial Progress
2nd Expenditure
of ₹ 1159603 (11.60 Lacs ) done.
Cummulative ₹ 18.27Lacs ( against 40.05Lacs )
on Friday, April 28th 2023, 6:30:00 pm
70%
Physical Progress
Physical Progress Reported at 3rd time
on Monday, October 30th 2023, 6:30:00 pm
75.57%
Financial Progress
3rd Expenditure
of ₹ 1200127 (12.00 Lacs ) done.
Cummulative ₹ 30.27Lacs ( against 40.05Lacs )
on Sunday, February 4th 2024, 6:30:00 pm
85.01%
Financial Progress
4th Expenditure
of ₹ 377844 (3.78 Lacs ) done.
Cummulative ₹ 34.05Lacs ( against 40.05Lacs )
on Monday, March 4th 2024, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 4th time
on Friday, May 30th 2025, 6:30:00 pm
97.69%
Financial Progress
5th Expenditure
of ₹ 508000 (5.08 Lacs ) done.
Cummulative ₹ 39.13Lacs ( against 40.05Lacs )
on Sunday, June 29th 2025, 6:30:00 pm
99.83%
Financial Progress
6th Expenditure
of ₹ 85525 (0.86 Lacs ) done.
Cummulative ₹ 39.98Lacs ( against 40.05Lacs )