on Monday, July 10th 2023, 6:30:00 pm
Work Sanctioned
निक्षेप मद के अन्तर्गत जिला न्यायालय के वैनुरेबल विटनेस डिपोजिशन सेंटर का निर्माण कार्य
on Friday, July 14th 2023, 8:16:47 am
Technical Sanction
of ₹ 13.85 Lacs
1st Technical Sanction of Work after survey,detailed design and analysis by Latter No. 17/1C
on Wednesday, November 29th 2023, 6:30:00 pm
49.22%
Financial Progress
1st Expenditure
of ₹ 681732 (6.82 Lacs ) done.
Cummulative ₹ 6.82Lacs ( against 13.85Lacs )
on Wednesday, December 6th 2023, 6:30:00 pm
100%
Physical Progress
Physical Progress Reported at 1st time
on Sunday, February 4th 2024, 6:30:00 pm
93.49%
Financial Progress
2nd Expenditure
of ₹ 613057 (6.13 Lacs ) done.
Cummulative ₹ 12.95Lacs ( against 13.85Lacs )